Acknowledgments |
|
xi | |
Dedication |
|
xv | |
About the Author |
|
xvii | |
Foreword |
|
xix | |
Preface |
|
xxiii | |
|
|
1 | (6) |
|
How Was That Even Remotely Possible? |
|
|
1 | (1) |
|
Why a Book About Kennedy Space Center? |
|
|
2 | (1) |
|
How This Book is Organized |
|
|
3 | (1) |
|
|
4 | (3) |
|
|
7 | (22) |
|
|
7 | (1) |
|
|
8 | (1) |
|
|
8 | (1) |
|
|
8 | (1) |
|
|
8 | (1) |
|
|
8 | (1) |
|
KSC and the Flight Hardware |
|
|
9 | (1) |
|
|
9 | (3) |
|
|
12 | (1) |
|
Managing Operations for Multiple Missions |
|
|
12 | (1) |
|
|
13 | (3) |
|
Rocco Petrone's Daily Staff Meeting |
|
|
16 | (1) |
|
|
17 | (1) |
|
The 72-Hour/11-Day Schedules and Snoopy |
|
|
18 | (6) |
|
|
24 | (1) |
|
Padding, Sandbagging, and Umbrellas |
|
|
25 | (1) |
|
Contractor Scheduling and Reporting |
|
|
26 | (1) |
|
|
27 | (2) |
|
3 Requirements, Tests, and Computerization |
|
|
29 | (38) |
|
Controlling the Configuration |
|
|
29 | (1) |
|
It All Started with Requirements |
|
|
29 | (2) |
|
Configuration Inspection Log and Engineering Orders |
|
|
31 | (1) |
|
Testing to the Requirements |
|
|
32 | (1) |
|
Test and Checkout Procedure (TCP) |
|
|
32 | (1) |
|
Test Preparation Sheet (TPS) |
|
|
32 | (1) |
|
Integrated Test Procedure (ITP) |
|
|
32 | (1) |
|
|
33 | (2) |
|
Test and Inspection Record (TAIR) |
|
|
35 | (1) |
|
Test Problem Report (TPR) |
|
|
36 | (1) |
|
Discrepancy Record (DR) and Material Review (MR) |
|
|
37 | (1) |
|
Roles in Test and Checkout |
|
|
38 | (1) |
|
Quality Control Inspection |
|
|
39 | (2) |
|
Developing Tests and Procedures |
|
|
41 | (2) |
|
|
43 | (1) |
|
|
44 | (2) |
|
|
46 | (1) |
|
|
46 | (2) |
|
Saturn Launch Computer Complex |
|
|
48 | (2) |
|
|
50 | (1) |
|
Launch Vehicle Test System Operation |
|
|
51 | (1) |
|
Other Launch Vehicle Computer Systems |
|
|
52 | (1) |
|
Digital Data Acquisition System |
|
|
52 | (1) |
|
Digital Events Evaluator (DEE) |
|
|
52 | (1) |
|
|
53 | (1) |
|
|
53 | (1) |
|
|
54 | (2) |
|
Spacecraft Testing with ACE |
|
|
56 | (1) |
|
The Quick-Look Data Station |
|
|
57 | (2) |
|
Central Instrumentation Facility (CIF) |
|
|
59 | (2) |
|
Timing and Countdown System |
|
|
61 | (1) |
|
Propellant Tanking Computer System |
|
|
61 | (2) |
|
Computers Were Vital to Success |
|
|
63 | (1) |
|
Was the Paperwork Worth It? |
|
|
64 | (3) |
|
4 The MSOB and the CSM Processing Flow |
|
|
67 | (58) |
|
Why Assemble and Test at Kennedy Space Center? |
|
|
67 | (1) |
|
|
68 | (1) |
|
The Command/Service Module (CSM) |
|
|
69 | (1) |
|
|
69 | (2) |
|
|
71 | (1) |
|
Block I and Block II CSMs |
|
|
72 | (1) |
|
|
72 | (2) |
|
The Launch Escape System (LES) |
|
|
74 | (2) |
|
Spacecraft/Lunar Module Adapter (SLA) |
|
|
76 | (1) |
|
The Hectic World of Spacecraft Operations |
|
|
77 | (3) |
|
Roles and Responsibilities |
|
|
80 | (1) |
|
|
80 | (1) |
|
|
80 | (6) |
|
Work on the Assembly and Checkout Floor |
|
|
86 | (3) |
|
|
89 | (1) |
|
Resident Apollo Spacecraft Program Office (RASPO) |
|
|
90 | (1) |
|
|
90 | (1) |
|
Working with the Astronauts |
|
|
91 | (1) |
|
Spacecraft Testing with ACE |
|
|
92 | (1) |
|
The Spacecraft Flow in the MSOB |
|
|
92 | (2) |
|
|
94 | (1) |
|
Week of January 20, 1969: L Minus 177 Days |
|
|
94 | (1) |
|
Week of January 27: L Minus 170 Days |
|
|
95 | (5) |
|
Week of February 3: L Minus 163 Days |
|
|
100 | (1) |
|
Week of February 10: L Minus 156 Days |
|
|
100 | (2) |
|
Weeks of February 17 and 24: L Minus 149 Days |
|
|
102 | (2) |
|
Week of March 3: L Minus 135 Days |
|
|
104 | (1) |
|
Week of March 10: L Minus 128 Days |
|
|
105 | (3) |
|
Week of March 17: L Minus 121 Days |
|
|
108 | (2) |
|
Week of March 24: L Minus 114 Days |
|
|
110 | (3) |
|
Week of March 31: L Minus 107 Days |
|
|
113 | (1) |
|
Week of April 7: L Minus 100 Days |
|
|
113 | (1) |
|
|
114 | (5) |
|
Skylab Orbital Workshop Modules and ASTP Docking Module |
|
|
119 | (6) |
|
|
125 | (48) |
|
|
125 | (1) |
|
Weeks of January 6 to January 20: L Minus 191 Days |
|
|
125 | (1) |
|
|
126 | (1) |
|
|
127 | (2) |
|
|
129 | (1) |
|
|
130 | (2) |
|
|
132 | (1) |
|
Week of January 27: L Minus 170 Days |
|
|
132 | (1) |
|
Week of February 3: L Minus 163 Days |
|
|
132 | (1) |
|
Week of February 10: L Minus 156 Days |
|
|
133 | (3) |
|
Week of February 17: L Minus 149 Days |
|
|
136 | (3) |
|
Week of February 24: L Minus 146 Days |
|
|
139 | (2) |
|
Week of March 3: L Minus 135 Days |
|
|
141 | (1) |
|
Week of March 10: L Minus 128 Days |
|
|
141 | (2) |
|
Week of March 17: L Minus 121 Days |
|
|
143 | (2) |
|
Week of March 24: L Minus 114 Days |
|
|
145 | (1) |
|
Week of March 31: L Minus 107 Days |
|
|
146 | (7) |
|
EASEP and ALSEP Processing |
|
|
153 | (2) |
|
Lunar Rover Processing on Apollo 15 Through 17 |
|
|
155 | (4) |
|
Final Spacecraft Assembly |
|
|
159 | (1) |
|
|
159 | (2) |
|
Mating the Lunar Module to the SLA |
|
|
161 | (3) |
|
Mating the Command/Service Module to the SLA |
|
|
164 | (1) |
|
|
165 | (8) |
|
6 The Launch Vehicle Processing Flow in the VAB |
|
|
173 | (54) |
|
The World of Launch Vehicle Operations |
|
|
173 | (1) |
|
|
174 | (2) |
|
The Saturn Launch Vehicles |
|
|
176 | (3) |
|
|
179 | (1) |
|
|
179 | (1) |
|
|
179 | (1) |
|
|
180 | (1) |
|
|
180 | (1) |
|
The Launch Vehicle Processing Flow |
|
|
180 | (1) |
|
Stage Checkout Prior to Delivery to KSC |
|
|
181 | (1) |
|
|
182 | (1) |
|
Weeks of January 20 to February 3: L Minus 177 Days |
|
|
182 | (1) |
|
Sabotage on Apollo 11's S-IVB in the VAB? |
|
|
183 | (3) |
|
The S-II Arrives: February 6, 1969 |
|
|
186 | (3) |
|
Week of February 17: L Minus 149 Days |
|
|
189 | (1) |
|
|
190 | (6) |
|
Week of February 24: L Minus 146 Days |
|
|
196 | (2) |
|
Week of March 3: L Minus 135 Days |
|
|
198 | (3) |
|
The S-II Spacer "Spool": AS-501/AS-502 |
|
|
201 | (8) |
|
|
209 | (1) |
|
Week of March 10: L Minus 128 Days |
|
|
210 | (1) |
|
Testing Protocol in Launch Vehicle Operations |
|
|
210 | (2) |
|
Week of March 17: L Minus 121 Days |
|
|
212 | (1) |
|
Week of March 24: L Minus 114 Days |
|
|
213 | (1) |
|
Week of March 31: L Minus 107 Days |
|
|
214 | (3) |
|
Week of April 7: L Minus 100 Days |
|
|
217 | (1) |
|
Stacking the Spacecraft: April 14, 1969 |
|
|
217 | (2) |
|
Week of May 5: L Minus 72 Days |
|
|
219 | (2) |
|
Week of May 12: L Minus 65 Days |
|
|
221 | (4) |
|
Week of May 19: L Minus 58 Days |
|
|
225 | (2) |
|
7 The Processing Flow at the Launch Pad |
|
|
227 | (38) |
|
The Processing Flow at the Launch Pad |
|
|
227 | (1) |
|
Week of May 19: L Minus 58 Days |
|
|
227 | (1) |
|
Rollout: Tuesday, May 20, 1969 |
|
|
228 | (5) |
|
Mating the LUT to the Pad |
|
|
233 | (1) |
|
Positioning the MSS to Work on the Spacecraft |
|
|
234 | (4) |
|
Week of May 26: L Minus 51 Days |
|
|
238 | (1) |
|
The Apollo 16 Bladder Incident |
|
|
239 | (3) |
|
Week of June 2: L Minus 44 Days |
|
|
242 | (1) |
|
Right Readiness Test (FRT) |
|
|
243 | (1) |
|
|
244 | (2) |
|
Last-Minute Problems and Changes to LM-5 |
|
|
246 | (6) |
|
Week of June 9: L Minus 37 Days |
|
|
252 | (1) |
|
|
252 | (4) |
|
Week of June 16: L Minus 30 Days |
|
|
256 | (5) |
|
Week of June 23: L Minus 23 Days |
|
|
261 | (4) |
|
8 Countdown Demonstration Test |
|
|
265 | (24) |
|
|
265 | (1) |
|
|
266 | (1) |
|
|
267 | (1) |
|
The Apollo 4 CDDT: "The Test from Hell" |
|
|
268 | (5) |
|
The Apollo 10 Fuel Tank Collapse |
|
|
273 | (2) |
|
The Apollo 13 Oxygen Cloud and Vehicles to Burn |
|
|
275 | (2) |
|
Week of June 30: L Minus 16 Days |
|
|
277 | (1) |
|
Three Strikes Against Apollo 13 During CDDT |
|
|
278 | (7) |
|
Week of July 7, 1969: L Minus 9 Days |
|
|
285 | (1) |
|
Is That a Cold Solder Joint? |
|
|
286 | (3) |
|
|
289 | (56) |
|
Introduction to Launch Countdown |
|
|
289 | (1) |
|
Launch Windows for Apollo 11 |
|
|
289 | (1) |
|
|
290 | (1) |
|
|
290 | (1) |
|
|
291 | (3) |
|
|
294 | (1) |
|
Launch Mission Rules Document |
|
|
295 | (1) |
|
Interrupting the Countdown |
|
|
296 | (3) |
|
Procedure Change Requests |
|
|
299 | (1) |
|
Staffing During Countdown |
|
|
299 | (1) |
|
|
300 | (1) |
|
|
301 | (1) |
|
|
302 | (1) |
|
Preparations Start: T Minus 130 Hours |
|
|
303 | (2) |
|
Pre-count: T Minus 93 Hours |
|
|
305 | (3) |
|
Countdown Start: T Minus 28 Hours |
|
|
308 | (2) |
|
|
310 | (2) |
|
|
312 | (1) |
|
|
313 | (4) |
|
|
317 | (1) |
|
Sidebar: The S-II Sensor Short |
|
|
318 | (3) |
|
Propellant Loading: T Minus 9 Hours |
|
|
321 | (2) |
|
Going on Station in the Final Hours |
|
|
323 | (1) |
|
|
324 | (5) |
|
LH2 Leak! T Minus 3 Hours 38 Minutes |
|
|
329 | (1) |
|
Astronauts on Board: T Minus 2 Hours 40 Minutes |
|
|
330 | (6) |
|
Recycle Point: T Minus 22 Minutes |
|
|
336 | (1) |
|
Terminal Count: T Minus 3 Minutes 10 Seconds |
|
|
337 | (1) |
|
Terminal Countdown Sequencer (TCS) |
|
|
337 | (1) |
|
|
337 | (1) |
|
Terminal Count to Liftoff |
|
|
338 | (7) |
|
10 Plus Time and Near Misses |
|
|
345 | (24) |
|
The Saturn V Takes Flight: T Zero |
|
|
345 | (6) |
|
|
351 | (1) |
|
|
352 | (2) |
|
|
354 | (2) |
|
|
356 | (1) |
|
|
356 | (1) |
|
|
356 | (1) |
|
Lessons Learned From Countdown And Launch |
|
|
356 | (1) |
|
AS-502 (Apollo 6): The Successful Failure |
|
|
357 | (2) |
|
The Apollo 12 Lightning Strike |
|
|
359 | (3) |
|
Apollo 17: Cutoff at T minus 30 Seconds |
|
|
362 | (3) |
|
Battle Damage in the Skylab Orbital Workshop Launch |
|
|
365 | (2) |
|
Skylab 2: Milliseconds from Disaster |
|
|
367 | (2) |
|
|
369 | (6) |
|
|
369 | (6) |
Appendix A Acronyms and Abbreviations |
|
375 | (6) |
Appendix B Missions with Apollo and Saturn Hardware |
|
381 | (10) |
Appendix C S-II Stage Checkout Tests |
|
391 | (10) |
Appendix D Apollo 11 OIS Call Signs |
|
401 | (8) |
Appendix E Firing Room Staffing During Apollo 11 and 14 Countdowns |
|
409 | (8) |
Appendix F Recommended Reading and References |
|
417 | (6) |
Appendix G Interviewees |
|
423 | (4) |
Index |
|
427 | |