Muutke küpsiste eelistusi

E-raamat: Nuclear Power Plant Development: Contract Issues, Claims and Disputes [Taylor & Francis e-raamat]

(Crown Office Chambers, UK)
  • Formaat: 552 pages, 2 Tables, black and white; 17 Line drawings, black and white; 17 Illustrations, black and white
  • Sari: Construction Practice Series
  • Ilmumisaeg: 16-Apr-2021
  • Kirjastus: CRC Press
  • ISBN-13: 9780429276958
  • Taylor & Francis e-raamat
  • Hind: 295,43 €*
  • * hind, mis tagab piiramatu üheaegsete kasutajate arvuga ligipääsu piiramatuks ajaks
  • Tavahind: 422,05 €
  • Säästad 30%
  • Formaat: 552 pages, 2 Tables, black and white; 17 Line drawings, black and white; 17 Illustrations, black and white
  • Sari: Construction Practice Series
  • Ilmumisaeg: 16-Apr-2021
  • Kirjastus: CRC Press
  • ISBN-13: 9780429276958
"Nuclear Power Plant Development covers the intricacies of developing a nuclear power plant project from a construction and legal standpoint. It deals with structuring, drafting, and negotiating a wide range of standard and specialised contracts relatingto the development of nuclear power-generation projects and also covers the other forms of power-generating facilities. It covers the forms of contract, the law involved internationally, and potential areas of pitfalls and how to avoid them in a systematic format covering various forms of projects. It is suitable for solicitors and barristers involved in the contracting for such facilities and the handling of litigation related to them, government officials involved in the commissioning and development of nuclear facilities for regional governments, and engineers and contractors involved in the actual work of design and contract administration and dispute resolution"--

Nuclear Power Plant Development covers the intricacies of developing a nuclear power plant project from a construction and legal standpoint. It deals with structuring, drafting, and negotiating a wide range of standard and specialised contracts relating to the development of nuclear power-generation projects and also covers the other forms of power-generating facilities. It covers the forms of contract, the law involved internationally, and potential areas of pitfalls and how to avoid them in a systematic format covering various forms of projects. It is suitable for solicitors and barristers involved in the contracting for such facilities and the handling of litigation related to them, government officials involved in the commissioning and development of nuclear facilities for regional governments, and engineers and contractors involved in the actual work of design and contract administration and dispute resolution.
Preface xvii
Acknowledgements xix
Table of Cases
xxi
Table of UK Legislation
xxxi
Table of International Legislation
xxxiii
Chapter 1 The Underlying Basics: Nuclear Energy and Reactors
1(10)
Nuclear Power
1(3)
Reactor Types and Designs
4(2)
Nuclear Reactor Systems
6(1)
Different Types of Systems -- Advantages and Disadvantages
7(1)
The Future
7(4)
Chapter 2 Nuclear Energy Engineering and Contracts Overview
11(36)
Preliminary steps
18(2)
Risk Measurement
20(1)
Who owns Risk?
21(1)
Risk Management
22(2)
Adverse Physical Conditions or Obstructions
24(1)
Delay and Disruption
24(1)
Defective Materials or Workmanship of Contractor
24(1)
Direction and Supervision by the Employer or the Engineer
24(1)
Damage and Injury to Persons and Property
25(1)
Shortage of Resources
25(1)
Government Policy and Change of Legislation
25(1)
Conflicts and war
25(1)
Labour Demands and Unrest
25(1)
Inflation
26(1)
Arbitration and Law
26(1)
Lump sum contracts
27(1)
Measurement Contracts
28(1)
Cost Reimbursement Contracts
28(1)
Cost plus percentage fee
28(1)
Design and build procurement
29(1)
For management procurement
30(1)
Management contracts
30(1)
Construction management
31(1)
Design, manage, construct and in some instances maintain
32(1)
The Joint Contracts Tribunal (JCT) Forms
32(1)
Main Forms
33(1)
The Main Contracts
34(1)
Smaller project contracts
34(1)
The Main Features
34(1)
Format and structure
35(1)
Main Provisions
35(1)
Design and Build Contract (DB)
36(1)
Standard Building Contract (SBC)
36(1)
Major Project Construction (MP)
37(1)
Main JCT contracts
37(1)
The Government Conditions of Contract, Gc Works
37(1)
The New Engineering Contract Documents (NEC3 and NEC4)
38(1)
The Engineering and Construction Contract (ECC)
39(1)
The Engineering and Construction Subcontract Contract (ECS)
40(1)
The Engineering and Construction Short Contract (ECSC)
40(1)
The Engineering and Construction Short Subcontract (ECSS)
40(1)
The Professional Services Contract (PSC)
40(1)
The Professional Services Short Contract (PSSC)
40(1)
Framework Contract (FC)
41(1)
Term Service Contract (TSC)
41(1)
Supply Contract/Short Supply Contract (SC/SSC)
41(1)
Adjudicator's Contract (AC)
41(1)
Guidance Notes and Flowcharts
41(2)
Specific Risks
43(1)
Adverse Ground or Physical Obstructions or Conditions on the Site
43(1)
Delay, Disruption of the Works
44(1)
Extensions of Time
45(1)
Summary
45(2)
Chapter 3 NPP Contract Issues at Inception, Standard form Contract Provisions: Regarding NPP Risk, Delay and Potential for Disruption
47(48)
EPC Contracts
47(3)
Forms of Standard Construction Contract
50(4)
The Guaranteed Maximum Price Contract
54(1)
The Remeasurement Type of Contract
55(1)
The Cost Reimbursement or Cost Plus Fee Contract
55(1)
Target Cost Contracts
55(1)
The ICE Conditions of Contract
56(1)
Measurement Version 7th Edition
56(1)
ICE Design and Construct Contract
56(1)
ICE Minor Works Contract
56(1)
Time and Cost Issues Under the Measurement Version, Design and Construct, Minor Works
57(1)
The NEC3 -- The New Engineering Contract Engineering and Construction Contract -- NEC ECC
58(1)
Overview
58(1)
Some Important Provisions
59(2)
Prevention Clause 19
61(1)
The Concept of Key Dates
61(1)
Design Liability
61(1)
Payment for Defective Work
61(3)
Contractor Incentives
64(1)
Variations
64(1)
Contractor's Rights and Obligations
65(1)
Additional Obligations and Issues
66(1)
Termination Issues
66(1)
Force Majeure
67(1)
The Silver Book
68(1)
Damages
68(20)
Sub-Clause 1.1.4.3
70(1)
Sub-Clause 1.1.6.9
70(1)
Sub-Clause 1.3 (Communications)
70(1)
Sub-Clause 1.9 (Delayed Drawings or Instructions)
71(1)
Sub-Clause 2.1 (Right of Access to the Site)
71(1)
Sub-Clause 3.3 (Instructions of the Engineer)
72(1)
Sub-Clause 3.5 (Determinations)
73(1)
Sub-Clause 4.7 (Setting Out)
73(1)
Sub-Clause 4.12 (Unforeseeable Physical Conditions)
74(1)
Sub-Clause 4.24 (Fossils)
75(1)
Sub-Clause 7.4 (Testing)
75(1)
Sub-Clause 8.1 (Commencement of Works)
76(1)
Sub-Clause 8.2 (Time for Completion)
76(1)
Sub-Clause 8.3 (Programme)
76(1)
Sub-Clause 8.4 (Extension of Time for Completion)
77(1)
Sub-Clause 8.5 (Delays Caused by Authorities)
78(1)
Sub-Clause 8.7 (Delay Damages)
78(3)
Sub-Clause 10.1 (Taking Over of the Works and Sections)
81(1)
Sub-Clause 10.3 (Interference with Tests on Completion)
82(1)
Sub-Clause 13.1 (Right to Vary)
83(1)
Sub-Clause 13.3 (Variation Procedure)
83(1)
Sub-Clause 13.7 (Adjustments for Changes in Legislation)
84(1)
Sub-Clause 16.1 (Contractor's Entitlement to Suspend Work)
84(1)
Sub-Clause 17.4 (Consequences of Employer's Risks)
85(1)
Sub-Clauses 19.1 (Definition of Force Majeure) and 19.4 (Consequences of Force Majeure)
85(1)
Sub-Clause 20.1 (Contractor's Claims)
86(2)
The Other Form Contracts Delaying with Delay
88(1)
The JCT Form Contract
88(1)
Extensions of time
88(1)
Clause 2.3.1.1 Delay events
88(1)
Clause 2.3.1.2 Delay notices
88(2)
2.3.1.3 Assessment
88(1)
2.3.1.4 Delay avoidance
89(1)
NEC3 Form of Contact 2013 (and the NEC4 2017)
90(1)
NEC3 terminology
90(1)
Delay events
91(1)
Delay notices
91(1)
Assessment
91(2)
ICE Conditions of Contract, 7th Edition
93(2)
Chapter 4 Bespoke NPP Agreement Terms and Conditions
95(104)
Sample Nuclear Power Plant Agreement
95(4)
Clause 1 Definitions
99(5)
Clause 2 Basis for the Plant Contract
104(4)
Clause 3 Scope of the Plant Contract
108(4)
Clause 4 Documents
112(9)
Clause 5 General Conditions
121(14)
Clause 6 Risks, Liabilities and Title
135(5)
Clause 7 Insurances
140(4)
Clause 8 Licensability and Licensing
144(4)
Clause 9 Training of Plant Personnel
148(1)
Clause 10 Pre-Operational Testing, Commissioning (including performance testing), Demonstration Run and Provisional Takeover
149(8)
Clause 11 Plant Contract Schedules
157(8)
Clause 12 Technical Guarantees
165(7)
Clause 13 Availability Guarantees
172(2)
Clause 14 Intellectual Property Rights
174(1)
Clause 15 Owner's Acceptance and Final Takeover
174(2)
Clause 16 Contractual Price
176(1)
Clause 17 Price Revisions for the Contractual Price
177(1)
Clause 18 Terms of Payment
178(2)
Clause 19 Execution of Payments
180(2)
Clause 20 Force Majeure
182(1)
Clause 21 Rejection of Plant and Termination of Plant Contract
183(5)
Clause 22 Applicable Law
188(1)
Clause 23 Jurisdiction, and Dispute Resolution
188(4)
Clause 24 Miscellaneous Conditions
192(3)
Clause 25 Availability of Spare Parts
195(2)
Clause 26 Severability
197(1)
Clause 27 Survival of Obligations; Non-Waiver
197(1)
Clause 28 Relationship of the Parties
197(1)
Clause 29 Entire Agreement and Amendments
197(1)
Clause 30 Transfer
198(1)
Chapter 5 Delay -- An Overview
199(32)
But what is complete and at what cost?
201(3)
Due Diligence Progression to Completion
204(1)
Complying with the Programme
205(1)
Standard Form Contract and Programming
206(1)
Delay -- Who Is at Fault?
206(1)
Force Majeure
206(2)
Is the Contract Terminated?
208(1)
Acts of God
209(1)
The Purpose of Force Majeure Clauses -- Historically and Internationally
210(2)
Typical Force Majeure Clause Usage Excusing Delay
212(1)
The Necessary Requirements for Force Majeure
212(1)
When Does Force Majeure Commence?
213(1)
The Duration of the Condition
213(1)
When Should Notice Be Given?
214(1)
Force Majeure's Effect
215(1)
Frustration
215(4)
Extension of Time
219(1)
Standard Forms -- Relevant Events and/or Compensation Events
220(1)
Concurrent Delay Issues
221(1)
Other Related Delay Issues
221(2)
Time Is of the Essence Provisions
223(4)
JCT, NEC3 and Others
227(1)
Delay Analysis --Methods and Types
228(1)
As-planned versus as-built
228(1)
Impacted as-planned
229(1)
Collapsed as-built
229(1)
Time impact analysis
229(1)
Critical Path
229(1)
"Float" of non-critical works
230(1)
Disruption
230(1)
Chapter 6 Delay Analysis Tools
231(56)
Delay and Disruption Claims
232(2)
Complexity
234(2)
Lack of a Uniform Approach
236(1)
Practical Considerations
237(2)
Delay Categories
239(2)
Delay Classifications
241(1)
Concurrent Delay Synopsis
241(6)
Float
247(1)
The Issue of Float
248(3)
Contractor's Right to Finish Early
251(1)
Net Effect Method
252(1)
Notification of Claim
253(2)
But Which Method?
255(1)
The Problem
256(3)
Information
259(3)
Deficiencies in Contractors' Programmes
262(1)
Reluctance
262(1)
Baseline Programme Problems
263(4)
Deficiencies in the Planning and Programming Process
267(4)
The Difference between Delay and Disruption
271(1)
The Methods
272(1)
The Methodologies
272(3)
Delay Analysis Methods Simplified
275(3)
Which Method Is Best?
278(1)
Disruption Analysis Methodologies
279(1)
The Measured Mile Technique
280(1)
Industry Studies and Guidelines
281(1)
Total Cost Method
282(1)
Modified total cost approach
283(1)
Time and Motion Studies
284(1)
System Dynamics Modelling Approach
284(1)
Earned Value Management (EVM)
284(1)
Final Overview
285(2)
Chapter 7 Construction Delay Analysis
287(24)
Summary diagram
290(1)
Foresight (forward-looking)
290(1)
Hindsight (backward-looking)
290(2)
Contemporaneous
292(1)
Delay Log
292(1)
Where the Problems start
292(1)
Requests for Information
293(1)
Typical Reasons and Costs -- the real world
294(7)
Critical Path
301(5)
Real-World of Delay
306(3)
Float
309(1)
Summary
309(2)
Chapter 8 Forensic Schedule Analysis and Discretionary Logic
311(18)
Time of performance
312(1)
Legal entitlement
312(3)
Technical entitlement -- Delay Analysis Techniques and analysis methods
315(2)
The Observational/Static/Gross (MIP 3.1)
317(1)
The Observational/Static/Periodic (MIP 3.2)
317(1)
The Observational/Dynamic/Contemporaneous As-Is (MIP 3.3)
317(1)
The Observational/Dynamic/Contemporaneous Split (MIP 3.4)
318(1)
The Observational/Dynamic/Modified or Recreated (MIP 3.5)
318(1)
The Modelled/Additive/Single Base (MIP 3.6)
319(1)
The Modelled/Additive/Multiple Base (MIP 3.7)
319(1)
The Modelled/Subtractive/Single Simulation (MIP 3.8)
319(1)
The Modelled/Subtractive/Multiple Base (MIP 3.9)
320(2)
Critical path method logic
322(1)
The advantage of forensic schedule analysis in the context of the management of arbitration/adjudication procedures
323(3)
Conclusion
326(3)
Chapter 9 Distortion of Delay Analysis
329(28)
Where to start
336(1)
Scenario 1
337(3)
Calendars
340(2)
Diagram Grouping and Sorting
342(5)
Constraints and Negative Total Float
347(4)
Labour Resources
351(1)
Other Areas for Deception
351(2)
Longest Path or Critical Path?
353(4)
Chapter 10 Unforeseen Ground Conditions
357(20)
The USA
363(2)
Contractor's Duty?
365(3)
Employer's Duty?
368(1)
Is Silence a Basis for a Claim?
369(1)
History
369(1)
Type 1 and Type 2 conditions
370(1)
Type 1
370(1)
Type 2
371(1)
Type 3
372(2)
Materiality
374(3)
Chapter 11 Claims for Extensions of Time
377(28)
The Risk Register in the Notice process
381(1)
Risk identification
382(1)
Risk analysis
382(1)
Warnings and Risk resolutions
382(1)
The Final Step -- Allocating Responsibility
383(1)
No Reply Needed
384(1)
The risk reduction meeting
385(1)
Difference between Early warnings, RFIs and TQs
385(2)
Preparing and Proving an EOT claim
387(1)
Creating a Systematic Approach to EOT Claims Documentation
387(1)
The Baseline Programme Planning
387(1)
Pre-planning tasks at the start
388(1)
Who Owns the Float?
389(1)
Who Owns the Float -- Standard Form Contracts
390(1)
JCT contracts
390(1)
NEC3 contracts
391(1)
ICE contracts
391(1)
Baseline Programme Checklist
391(2)
Programme updates
393(2)
Changes to the Baseline Programme -- Revisions
395(1)
Identifying and Quantifying the delays to the programme updates
396(2)
Categorisation of Delay
398(1)
Risk Events versus Delay
398(2)
Documenting delays
400(1)
Concurrent Delay
400(1)
Records
401(1)
The Approval Process
401(4)
Chapter 12 Constructive Acceleration
405(10)
The Requirements
406(1)
Constructive Acceleration
407(2)
The Courts in the UK and the USA
409(6)
Chapter 13 Notice Requirements
415(28)
When Exactly does the 28-Day Notice Period Commence?
415(6)
Who Exactly at the Contractor is Supposed to Acquire Knowledge of the Event or Circumstance?
421(4)
Type of Records and Claim
425(1)
The Need for Proper Records as Part of the Claim Submission
426(1)
Has the Dispute Crystallised and can it be Enforced?
427(1)
Is There a Dispute to Enforce?
427(3)
The Standard Forms
430(2)
Prevention
432(9)
But When Does the Delay Impact the Critical Path?
441(2)
Chapter 14 Legal Systems
443(36)
The Common Law
443(1)
History
444(4)
Common Law Countries
448(1)
Civil Law
449(1)
The Napoleonic Code
449(2)
Differences Between Common and Civil Law
451(1)
Sharia -- Islamic Law
452(1)
History
452(5)
Enforcement of Adjudication Decisions versus arbitration awards
457(3)
Dispute Resolution in Delay and Construction Matters
460(2)
Other Dispute Resolution Methods
462(1)
The Engineer/Arbitrator as Judge
463(1)
The Engineer as Quasi-Arbitrator
464(3)
Non-Statutory Adjudication
467(2)
The Advent of Dispute Boards in England
469(1)
Extension to International Cases
470(4)
Specific Regional Differences and Methods
474(5)
Chapter 15 Dispute Resolution Methods
479(32)
The Dispute Board Concept
481(1)
Mediation
481(1)
Arbitration
481(1)
Litigation
482(1)
Dispute Board
482(1)
What is a dispute board?
483(2)
What makes a dispute board unique? What can be achieved by using a dispute board?
485(1)
Recommendations versus Binding Decisions
486(1)
Non-binding recommendations
486(1)
Interim-binding decisions
487(1)
Differences between dispute boards and arbitration, mediation, adjudication and alternative dispute resolution (ADR)
488(2)
Mediation
490(1)
Ancient Cultures
491(1)
Early China
492(1)
Qing Dynasty -- Three Steps of Mediation
493(1)
The First Step
493(1)
The Second Step
494(1)
The Third Step
494(1)
USA
495(1)
Change of Direction
495(1)
United Kingdom
496(2)
Islamic Tradition
498(2)
Global Reach
500(1)
The Development of Commercial Construction Mediation in the United Kingdom
500(1)
Woolf Reforms
501(1)
CPR Rules
502(1)
Building and Construction Disputes
502(1)
Halsey
503(3)
Failure to Mediate Justified
506(1)
Limited Circumstances
506(2)
Enforcing Mediation
508(1)
The Continuum of Dispute resolution
509(2)
Index 511
Dr Cyril Chern is a Barrister practising at 4 New Square Chambers, London. He has practised since 1972, specifically in the areas of engineering and construction disputes in the United Kingdom, the EU and internationally. Not only is he a highly praised and respected Barrister, he is also a Chartered Architect, Chartered Arbitrator, Accredited Mediator, Adjudicator, and Engineer and has written widely on Construction Disputes, Construction Law, and Mediation. He also teaches Dispute Board Courses for the World Bank/International Finance Corporation, FIDIC and the Dispute Board Federation (Geneva), as well as the comprehensive advanced FIDIC contracts course and commercial mediation for the Bar Council Mediation seminar, the World Bank, the IFC, and the DBF.