| Preface |
|
xvii | |
| Acknowledgements |
|
xix | |
|
|
|
xxi | |
|
|
|
xxxi | |
|
Table of International Legislation |
|
|
xxxiii | |
|
Chapter 1 The Underlying Basics: Nuclear Energy and Reactors |
|
|
1 | (10) |
|
|
|
1 | (3) |
|
Reactor Types and Designs |
|
|
4 | (2) |
|
|
|
6 | (1) |
|
Different Types of Systems -- Advantages and Disadvantages |
|
|
7 | (1) |
|
|
|
7 | (4) |
|
Chapter 2 Nuclear Energy Engineering and Contracts Overview |
|
|
11 | (36) |
|
|
|
18 | (2) |
|
|
|
20 | (1) |
|
|
|
21 | (1) |
|
|
|
22 | (2) |
|
Adverse Physical Conditions or Obstructions |
|
|
24 | (1) |
|
|
|
24 | (1) |
|
Defective Materials or Workmanship of Contractor |
|
|
24 | (1) |
|
Direction and Supervision by the Employer or the Engineer |
|
|
24 | (1) |
|
Damage and Injury to Persons and Property |
|
|
25 | (1) |
|
|
|
25 | (1) |
|
Government Policy and Change of Legislation |
|
|
25 | (1) |
|
|
|
25 | (1) |
|
Labour Demands and Unrest |
|
|
25 | (1) |
|
|
|
26 | (1) |
|
|
|
26 | (1) |
|
|
|
27 | (1) |
|
|
|
28 | (1) |
|
Cost Reimbursement Contracts |
|
|
28 | (1) |
|
|
|
28 | (1) |
|
Design and build procurement |
|
|
29 | (1) |
|
For management procurement |
|
|
30 | (1) |
|
|
|
30 | (1) |
|
|
|
31 | (1) |
|
Design, manage, construct and in some instances maintain |
|
|
32 | (1) |
|
The Joint Contracts Tribunal (JCT) Forms |
|
|
32 | (1) |
|
|
|
33 | (1) |
|
|
|
34 | (1) |
|
Smaller project contracts |
|
|
34 | (1) |
|
|
|
34 | (1) |
|
|
|
35 | (1) |
|
|
|
35 | (1) |
|
Design and Build Contract (DB) |
|
|
36 | (1) |
|
Standard Building Contract (SBC) |
|
|
36 | (1) |
|
Major Project Construction (MP) |
|
|
37 | (1) |
|
|
|
37 | (1) |
|
The Government Conditions of Contract, Gc Works |
|
|
37 | (1) |
|
The New Engineering Contract Documents (NEC3 and NEC4) |
|
|
38 | (1) |
|
The Engineering and Construction Contract (ECC) |
|
|
39 | (1) |
|
The Engineering and Construction Subcontract Contract (ECS) |
|
|
40 | (1) |
|
The Engineering and Construction Short Contract (ECSC) |
|
|
40 | (1) |
|
The Engineering and Construction Short Subcontract (ECSS) |
|
|
40 | (1) |
|
The Professional Services Contract (PSC) |
|
|
40 | (1) |
|
The Professional Services Short Contract (PSSC) |
|
|
40 | (1) |
|
|
|
41 | (1) |
|
Term Service Contract (TSC) |
|
|
41 | (1) |
|
Supply Contract/Short Supply Contract (SC/SSC) |
|
|
41 | (1) |
|
Adjudicator's Contract (AC) |
|
|
41 | (1) |
|
Guidance Notes and Flowcharts |
|
|
41 | (2) |
|
|
|
43 | (1) |
|
Adverse Ground or Physical Obstructions or Conditions on the Site |
|
|
43 | (1) |
|
Delay, Disruption of the Works |
|
|
44 | (1) |
|
|
|
45 | (1) |
|
|
|
45 | (2) |
|
Chapter 3 NPP Contract Issues at Inception, Standard form Contract Provisions: Regarding NPP Risk, Delay and Potential for Disruption |
|
|
47 | (48) |
|
|
|
47 | (3) |
|
Forms of Standard Construction Contract |
|
|
50 | (4) |
|
The Guaranteed Maximum Price Contract |
|
|
54 | (1) |
|
The Remeasurement Type of Contract |
|
|
55 | (1) |
|
The Cost Reimbursement or Cost Plus Fee Contract |
|
|
55 | (1) |
|
|
|
55 | (1) |
|
The ICE Conditions of Contract |
|
|
56 | (1) |
|
Measurement Version 7th Edition |
|
|
56 | (1) |
|
ICE Design and Construct Contract |
|
|
56 | (1) |
|
|
|
56 | (1) |
|
Time and Cost Issues Under the Measurement Version, Design and Construct, Minor Works |
|
|
57 | (1) |
|
The NEC3 -- The New Engineering Contract Engineering and Construction Contract -- NEC ECC |
|
|
58 | (1) |
|
|
|
58 | (1) |
|
Some Important Provisions |
|
|
59 | (2) |
|
|
|
61 | (1) |
|
|
|
61 | (1) |
|
|
|
61 | (1) |
|
Payment for Defective Work |
|
|
61 | (3) |
|
|
|
64 | (1) |
|
|
|
64 | (1) |
|
Contractor's Rights and Obligations |
|
|
65 | (1) |
|
Additional Obligations and Issues |
|
|
66 | (1) |
|
|
|
66 | (1) |
|
|
|
67 | (1) |
|
|
|
68 | (1) |
|
|
|
68 | (20) |
|
|
|
70 | (1) |
|
|
|
70 | (1) |
|
Sub-Clause 1.3 (Communications) |
|
|
70 | (1) |
|
Sub-Clause 1.9 (Delayed Drawings or Instructions) |
|
|
71 | (1) |
|
Sub-Clause 2.1 (Right of Access to the Site) |
|
|
71 | (1) |
|
Sub-Clause 3.3 (Instructions of the Engineer) |
|
|
72 | (1) |
|
Sub-Clause 3.5 (Determinations) |
|
|
73 | (1) |
|
Sub-Clause 4.7 (Setting Out) |
|
|
73 | (1) |
|
Sub-Clause 4.12 (Unforeseeable Physical Conditions) |
|
|
74 | (1) |
|
Sub-Clause 4.24 (Fossils) |
|
|
75 | (1) |
|
|
|
75 | (1) |
|
Sub-Clause 8.1 (Commencement of Works) |
|
|
76 | (1) |
|
Sub-Clause 8.2 (Time for Completion) |
|
|
76 | (1) |
|
Sub-Clause 8.3 (Programme) |
|
|
76 | (1) |
|
Sub-Clause 8.4 (Extension of Time for Completion) |
|
|
77 | (1) |
|
Sub-Clause 8.5 (Delays Caused by Authorities) |
|
|
78 | (1) |
|
Sub-Clause 8.7 (Delay Damages) |
|
|
78 | (3) |
|
Sub-Clause 10.1 (Taking Over of the Works and Sections) |
|
|
81 | (1) |
|
Sub-Clause 10.3 (Interference with Tests on Completion) |
|
|
82 | (1) |
|
Sub-Clause 13.1 (Right to Vary) |
|
|
83 | (1) |
|
Sub-Clause 13.3 (Variation Procedure) |
|
|
83 | (1) |
|
Sub-Clause 13.7 (Adjustments for Changes in Legislation) |
|
|
84 | (1) |
|
Sub-Clause 16.1 (Contractor's Entitlement to Suspend Work) |
|
|
84 | (1) |
|
Sub-Clause 17.4 (Consequences of Employer's Risks) |
|
|
85 | (1) |
|
Sub-Clauses 19.1 (Definition of Force Majeure) and 19.4 (Consequences of Force Majeure) |
|
|
85 | (1) |
|
Sub-Clause 20.1 (Contractor's Claims) |
|
|
86 | (2) |
|
The Other Form Contracts Delaying with Delay |
|
|
88 | (1) |
|
|
|
88 | (1) |
|
|
|
88 | (1) |
|
Clause 2.3.1.1 Delay events |
|
|
88 | (1) |
|
Clause 2.3.1.2 Delay notices |
|
|
88 | (2) |
|
|
|
88 | (1) |
|
|
|
89 | (1) |
|
NEC3 Form of Contact 2013 (and the NEC4 2017) |
|
|
90 | (1) |
|
|
|
90 | (1) |
|
|
|
91 | (1) |
|
|
|
91 | (1) |
|
|
|
91 | (2) |
|
ICE Conditions of Contract, 7th Edition |
|
|
93 | (2) |
|
Chapter 4 Bespoke NPP Agreement Terms and Conditions |
|
|
95 | (104) |
|
Sample Nuclear Power Plant Agreement |
|
|
95 | (4) |
|
|
|
99 | (5) |
|
Clause 2 Basis for the Plant Contract |
|
|
104 | (4) |
|
Clause 3 Scope of the Plant Contract |
|
|
108 | (4) |
|
|
|
112 | (9) |
|
Clause 5 General Conditions |
|
|
121 | (14) |
|
Clause 6 Risks, Liabilities and Title |
|
|
135 | (5) |
|
|
|
140 | (4) |
|
Clause 8 Licensability and Licensing |
|
|
144 | (4) |
|
Clause 9 Training of Plant Personnel |
|
|
148 | (1) |
|
Clause 10 Pre-Operational Testing, Commissioning (including performance testing), Demonstration Run and Provisional Takeover |
|
|
149 | (8) |
|
Clause 11 Plant Contract Schedules |
|
|
157 | (8) |
|
Clause 12 Technical Guarantees |
|
|
165 | (7) |
|
Clause 13 Availability Guarantees |
|
|
172 | (2) |
|
Clause 14 Intellectual Property Rights |
|
|
174 | (1) |
|
Clause 15 Owner's Acceptance and Final Takeover |
|
|
174 | (2) |
|
Clause 16 Contractual Price |
|
|
176 | (1) |
|
Clause 17 Price Revisions for the Contractual Price |
|
|
177 | (1) |
|
Clause 18 Terms of Payment |
|
|
178 | (2) |
|
Clause 19 Execution of Payments |
|
|
180 | (2) |
|
|
|
182 | (1) |
|
Clause 21 Rejection of Plant and Termination of Plant Contract |
|
|
183 | (5) |
|
|
|
188 | (1) |
|
Clause 23 Jurisdiction, and Dispute Resolution |
|
|
188 | (4) |
|
Clause 24 Miscellaneous Conditions |
|
|
192 | (3) |
|
Clause 25 Availability of Spare Parts |
|
|
195 | (2) |
|
|
|
197 | (1) |
|
Clause 27 Survival of Obligations; Non-Waiver |
|
|
197 | (1) |
|
Clause 28 Relationship of the Parties |
|
|
197 | (1) |
|
Clause 29 Entire Agreement and Amendments |
|
|
197 | (1) |
|
|
|
198 | (1) |
|
Chapter 5 Delay -- An Overview |
|
|
199 | (32) |
|
But what is complete and at what cost? |
|
|
201 | (3) |
|
Due Diligence Progression to Completion |
|
|
204 | (1) |
|
Complying with the Programme |
|
|
205 | (1) |
|
Standard Form Contract and Programming |
|
|
206 | (1) |
|
Delay -- Who Is at Fault? |
|
|
206 | (1) |
|
|
|
206 | (2) |
|
Is the Contract Terminated? |
|
|
208 | (1) |
|
|
|
209 | (1) |
|
The Purpose of Force Majeure Clauses -- Historically and Internationally |
|
|
210 | (2) |
|
Typical Force Majeure Clause Usage Excusing Delay |
|
|
212 | (1) |
|
The Necessary Requirements for Force Majeure |
|
|
212 | (1) |
|
When Does Force Majeure Commence? |
|
|
213 | (1) |
|
The Duration of the Condition |
|
|
213 | (1) |
|
When Should Notice Be Given? |
|
|
214 | (1) |
|
|
|
215 | (1) |
|
|
|
215 | (4) |
|
|
|
219 | (1) |
|
Standard Forms -- Relevant Events and/or Compensation Events |
|
|
220 | (1) |
|
|
|
221 | (1) |
|
Other Related Delay Issues |
|
|
221 | (2) |
|
Time Is of the Essence Provisions |
|
|
223 | (4) |
|
|
|
227 | (1) |
|
Delay Analysis --Methods and Types |
|
|
228 | (1) |
|
As-planned versus as-built |
|
|
228 | (1) |
|
|
|
229 | (1) |
|
|
|
229 | (1) |
|
|
|
229 | (1) |
|
|
|
229 | (1) |
|
"Float" of non-critical works |
|
|
230 | (1) |
|
|
|
230 | (1) |
|
Chapter 6 Delay Analysis Tools |
|
|
231 | (56) |
|
Delay and Disruption Claims |
|
|
232 | (2) |
|
|
|
234 | (2) |
|
Lack of a Uniform Approach |
|
|
236 | (1) |
|
|
|
237 | (2) |
|
|
|
239 | (2) |
|
|
|
241 | (1) |
|
Concurrent Delay Synopsis |
|
|
241 | (6) |
|
|
|
247 | (1) |
|
|
|
248 | (3) |
|
Contractor's Right to Finish Early |
|
|
251 | (1) |
|
|
|
252 | (1) |
|
|
|
253 | (2) |
|
|
|
255 | (1) |
|
|
|
256 | (3) |
|
|
|
259 | (3) |
|
Deficiencies in Contractors' Programmes |
|
|
262 | (1) |
|
|
|
262 | (1) |
|
Baseline Programme Problems |
|
|
263 | (4) |
|
Deficiencies in the Planning and Programming Process |
|
|
267 | (4) |
|
The Difference between Delay and Disruption |
|
|
271 | (1) |
|
|
|
272 | (1) |
|
|
|
272 | (3) |
|
Delay Analysis Methods Simplified |
|
|
275 | (3) |
|
|
|
278 | (1) |
|
Disruption Analysis Methodologies |
|
|
279 | (1) |
|
The Measured Mile Technique |
|
|
280 | (1) |
|
Industry Studies and Guidelines |
|
|
281 | (1) |
|
|
|
282 | (1) |
|
Modified total cost approach |
|
|
283 | (1) |
|
|
|
284 | (1) |
|
System Dynamics Modelling Approach |
|
|
284 | (1) |
|
Earned Value Management (EVM) |
|
|
284 | (1) |
|
|
|
285 | (2) |
|
Chapter 7 Construction Delay Analysis |
|
|
287 | (24) |
|
|
|
290 | (1) |
|
Foresight (forward-looking) |
|
|
290 | (1) |
|
Hindsight (backward-looking) |
|
|
290 | (2) |
|
|
|
292 | (1) |
|
|
|
292 | (1) |
|
|
|
292 | (1) |
|
|
|
293 | (1) |
|
Typical Reasons and Costs -- the real world |
|
|
294 | (7) |
|
|
|
301 | (5) |
|
|
|
306 | (3) |
|
|
|
309 | (1) |
|
|
|
309 | (2) |
|
Chapter 8 Forensic Schedule Analysis and Discretionary Logic |
|
|
311 | (18) |
|
|
|
312 | (1) |
|
|
|
312 | (3) |
|
Technical entitlement -- Delay Analysis Techniques and analysis methods |
|
|
315 | (2) |
|
The Observational/Static/Gross (MIP 3.1) |
|
|
317 | (1) |
|
The Observational/Static/Periodic (MIP 3.2) |
|
|
317 | (1) |
|
The Observational/Dynamic/Contemporaneous As-Is (MIP 3.3) |
|
|
317 | (1) |
|
The Observational/Dynamic/Contemporaneous Split (MIP 3.4) |
|
|
318 | (1) |
|
The Observational/Dynamic/Modified or Recreated (MIP 3.5) |
|
|
318 | (1) |
|
The Modelled/Additive/Single Base (MIP 3.6) |
|
|
319 | (1) |
|
The Modelled/Additive/Multiple Base (MIP 3.7) |
|
|
319 | (1) |
|
The Modelled/Subtractive/Single Simulation (MIP 3.8) |
|
|
319 | (1) |
|
The Modelled/Subtractive/Multiple Base (MIP 3.9) |
|
|
320 | (2) |
|
Critical path method logic |
|
|
322 | (1) |
|
The advantage of forensic schedule analysis in the context of the management of arbitration/adjudication procedures |
|
|
323 | (3) |
|
|
|
326 | (3) |
|
Chapter 9 Distortion of Delay Analysis |
|
|
329 | (28) |
|
|
|
336 | (1) |
|
|
|
337 | (3) |
|
|
|
340 | (2) |
|
Diagram Grouping and Sorting |
|
|
342 | (5) |
|
Constraints and Negative Total Float |
|
|
347 | (4) |
|
|
|
351 | (1) |
|
Other Areas for Deception |
|
|
351 | (2) |
|
Longest Path or Critical Path? |
|
|
353 | (4) |
|
Chapter 10 Unforeseen Ground Conditions |
|
|
357 | (20) |
|
|
|
363 | (2) |
|
|
|
365 | (3) |
|
|
|
368 | (1) |
|
Is Silence a Basis for a Claim? |
|
|
369 | (1) |
|
|
|
369 | (1) |
|
Type 1 and Type 2 conditions |
|
|
370 | (1) |
|
|
|
370 | (1) |
|
|
|
371 | (1) |
|
|
|
372 | (2) |
|
|
|
374 | (3) |
|
Chapter 11 Claims for Extensions of Time |
|
|
377 | (28) |
|
The Risk Register in the Notice process |
|
|
381 | (1) |
|
|
|
382 | (1) |
|
|
|
382 | (1) |
|
Warnings and Risk resolutions |
|
|
382 | (1) |
|
The Final Step -- Allocating Responsibility |
|
|
383 | (1) |
|
|
|
384 | (1) |
|
The risk reduction meeting |
|
|
385 | (1) |
|
Difference between Early warnings, RFIs and TQs |
|
|
385 | (2) |
|
Preparing and Proving an EOT claim |
|
|
387 | (1) |
|
Creating a Systematic Approach to EOT Claims Documentation |
|
|
387 | (1) |
|
The Baseline Programme Planning |
|
|
387 | (1) |
|
Pre-planning tasks at the start |
|
|
388 | (1) |
|
|
|
389 | (1) |
|
Who Owns the Float -- Standard Form Contracts |
|
|
390 | (1) |
|
|
|
390 | (1) |
|
|
|
391 | (1) |
|
|
|
391 | (1) |
|
Baseline Programme Checklist |
|
|
391 | (2) |
|
|
|
393 | (2) |
|
Changes to the Baseline Programme -- Revisions |
|
|
395 | (1) |
|
Identifying and Quantifying the delays to the programme updates |
|
|
396 | (2) |
|
|
|
398 | (1) |
|
|
|
398 | (2) |
|
|
|
400 | (1) |
|
|
|
400 | (1) |
|
|
|
401 | (1) |
|
|
|
401 | (4) |
|
Chapter 12 Constructive Acceleration |
|
|
405 | (10) |
|
|
|
406 | (1) |
|
Constructive Acceleration |
|
|
407 | (2) |
|
The Courts in the UK and the USA |
|
|
409 | (6) |
|
Chapter 13 Notice Requirements |
|
|
415 | (28) |
|
When Exactly does the 28-Day Notice Period Commence? |
|
|
415 | (6) |
|
Who Exactly at the Contractor is Supposed to Acquire Knowledge of the Event or Circumstance? |
|
|
421 | (4) |
|
Type of Records and Claim |
|
|
425 | (1) |
|
The Need for Proper Records as Part of the Claim Submission |
|
|
426 | (1) |
|
Has the Dispute Crystallised and can it be Enforced? |
|
|
427 | (1) |
|
Is There a Dispute to Enforce? |
|
|
427 | (3) |
|
|
|
430 | (2) |
|
|
|
432 | (9) |
|
But When Does the Delay Impact the Critical Path? |
|
|
441 | (2) |
|
|
|
443 | (36) |
|
|
|
443 | (1) |
|
|
|
444 | (4) |
|
|
|
448 | (1) |
|
|
|
449 | (1) |
|
|
|
449 | (2) |
|
Differences Between Common and Civil Law |
|
|
451 | (1) |
|
|
|
452 | (1) |
|
|
|
452 | (5) |
|
Enforcement of Adjudication Decisions versus arbitration awards |
|
|
457 | (3) |
|
Dispute Resolution in Delay and Construction Matters |
|
|
460 | (2) |
|
Other Dispute Resolution Methods |
|
|
462 | (1) |
|
The Engineer/Arbitrator as Judge |
|
|
463 | (1) |
|
The Engineer as Quasi-Arbitrator |
|
|
464 | (3) |
|
Non-Statutory Adjudication |
|
|
467 | (2) |
|
The Advent of Dispute Boards in England |
|
|
469 | (1) |
|
Extension to International Cases |
|
|
470 | (4) |
|
Specific Regional Differences and Methods |
|
|
474 | (5) |
|
Chapter 15 Dispute Resolution Methods |
|
|
479 | (32) |
|
The Dispute Board Concept |
|
|
481 | (1) |
|
|
|
481 | (1) |
|
|
|
481 | (1) |
|
|
|
482 | (1) |
|
|
|
482 | (1) |
|
|
|
483 | (2) |
|
What makes a dispute board unique? What can be achieved by using a dispute board? |
|
|
485 | (1) |
|
Recommendations versus Binding Decisions |
|
|
486 | (1) |
|
Non-binding recommendations |
|
|
486 | (1) |
|
Interim-binding decisions |
|
|
487 | (1) |
|
Differences between dispute boards and arbitration, mediation, adjudication and alternative dispute resolution (ADR) |
|
|
488 | (2) |
|
|
|
490 | (1) |
|
|
|
491 | (1) |
|
|
|
492 | (1) |
|
Qing Dynasty -- Three Steps of Mediation |
|
|
493 | (1) |
|
|
|
493 | (1) |
|
|
|
494 | (1) |
|
|
|
494 | (1) |
|
|
|
495 | (1) |
|
|
|
495 | (1) |
|
|
|
496 | (2) |
|
|
|
498 | (2) |
|
|
|
500 | (1) |
|
The Development of Commercial Construction Mediation in the United Kingdom |
|
|
500 | (1) |
|
|
|
501 | (1) |
|
|
|
502 | (1) |
|
Building and Construction Disputes |
|
|
502 | (1) |
|
|
|
503 | (3) |
|
Failure to Mediate Justified |
|
|
506 | (1) |
|
|
|
506 | (2) |
|
|
|
508 | (1) |
|
The Continuum of Dispute resolution |
|
|
509 | (2) |
| Index |
|
511 | |