List of Figures |
|
xix | |
List of Tables |
|
xxiii | |
Preface |
|
xxvii | |
Acknowledgements |
|
xxix | |
Author |
|
xxxi | |
Chapter 1 Introduction |
|
1 | (8) |
|
1.1 The Contents of This Book |
|
|
2 | (5) |
|
1.2 How to Read and Use This Book |
|
|
7 | (1) |
|
|
8 | (1) |
Chapter 2 The Seven Interdependent P's of a Project |
|
9 | (46) |
|
|
10 | (32) |
|
|
10 | (8) |
|
2.1.1.1 Critical Thinking |
|
|
11 | (1) |
|
|
12 | (1) |
|
2.1.1.3 The Two Distinct Types of Systems Thinking |
|
|
12 | (2) |
|
2.1.1.4 Beyond Systems Thinking |
|
|
14 | (4) |
|
2.1.2 Categories of People |
|
|
18 | (1) |
|
2.1.2.1 The Five Ways of Approaching Problems |
|
|
18 | (1) |
|
2.1.2.2 The Five Levels of Critical Thinking |
|
|
18 | (1) |
|
|
19 | (3) |
|
|
21 | (1) |
|
|
22 | (5) |
|
2.1.4.1 Externals and Internals |
|
|
23 | (1) |
|
2.1.4.2 McGregor's Theory X and Theory Y |
|
|
23 | (1) |
|
2.1.4.3 Maslow's Hierarchical Classification of Needs |
|
|
24 | (1) |
|
2.1.4.4 The Herzberg Motivation-Hygiene Theory |
|
|
25 | (1) |
|
2.1.4.5 Recognition and Rewards |
|
|
25 | (1) |
|
2.1.4.6 Expectations Affect Performance |
|
|
26 | (1) |
|
|
26 | (1) |
|
|
27 | (1) |
|
|
28 | (6) |
|
2.1.6.1 Formal Written Communications |
|
|
29 | (1) |
|
2.1.6.2 Formal Verbal Communications |
|
|
29 | (5) |
|
|
34 | (3) |
|
2.1.7.1 Cultural Differences in Perception |
|
|
35 | (1) |
|
|
35 | |
|
|
15 | (22) |
|
2.1.7.4 Signal-to-Noise Ratio |
|
|
37 | (1) |
|
2.1.8 Mitigating the Effect of and Overcoming Miscommunications |
|
|
37 | (5) |
|
|
37 | (4) |
|
|
41 | (1) |
|
|
41 | (1) |
|
|
42 | (4) |
|
2.2.1 Positive Use of Politics |
|
|
44 | (1) |
|
2.2.2 Negative Use of Politics |
|
|
44 | (1) |
|
2.2.3 Seven Steps That a Project Manager Can Take to Become Politically Astute |
|
|
45 | (1) |
|
|
46 | (1) |
|
|
47 | (1) |
|
|
47 | (2) |
|
2.5.1 The Process Timeline |
|
|
48 | (1) |
|
2.5.2 The Three Streams of Activities |
|
|
48 | (1) |
|
|
49 | (1) |
|
|
50 | (1) |
|
|
50 | (1) |
|
|
50 | (5) |
Chapter 3 Perceptions of Problem-Solving |
|
55 | (42) |
|
|
55 | (4) |
|
3.1.1 Assumptions Underlying Formal Problem-Solving |
|
|
55 | (1) |
|
3.1.2 Selected Myths of Problem-Solving |
|
|
56 | (3) |
|
3.1.2.1 All Problems Can Be Solved |
|
|
56 | (1) |
|
3.1.2.2 All Problems Have a Single Correct Solution |
|
|
57 | (1) |
|
3.1.2.3 The Problem-Solving Process is a Linear Time-Ordered Sequence |
|
|
58 | (1) |
|
3.1.2.4 One Problem-Solving Approach Can Solve All Problems |
|
|
59 | (1) |
|
|
59 | (2) |
|
3.2.1 Components of Problems |
|
|
59 | (2) |
|
|
61 | (1) |
|
3.3.1 Classifications of Problems |
|
|
61 | (1) |
|
3.3.2 The Level of Difficulty of Problems |
|
|
61 | (1) |
|
|
62 | (10) |
|
3.4.1 Problems and Symptoms |
|
|
62 | (1) |
|
3.4.2 The Difference between the Quality of the Decision and the Quality of the Outcome |
|
|
63 | (1) |
|
3.4.3 The Different Decision Outcomes |
|
|
63 | (4) |
|
3.4.3.1 Sources of Unanticipated Consequences or Outcomes of Decisions |
|
|
65 | (2) |
|
3.4.4 Research and Intervention Problems |
|
|
67 | (3) |
|
3.4.4.1 Research Problems |
|
|
67 | (2) |
|
3.4.4.2 Intervention Problems |
|
|
69 | (1) |
|
3.4.5 The Different Categories of Problems |
|
|
70 | (1) |
|
3.4.5.1 Well-Structured Problems |
|
|
70 | (1) |
|
3.4.5.2 Ill-Structured Problems |
|
|
71 | (1) |
|
|
71 | (1) |
|
3.4.6 The Different Domains of a Problem |
|
|
71 | (1) |
|
3.4.7 The Technological System Implementation Continuum |
|
|
72 | (1) |
|
|
72 | (1) |
|
|
72 | (1) |
|
3.5.1.1 Decision-Making Tools |
|
|
73 | (1) |
|
|
73 | (3) |
|
3.6.1 The Simple Problem-Solving Process |
|
|
74 | (1) |
|
3.6.2 The Extended Problem-Solving Process |
|
|
74 | (2) |
|
|
76 | (2) |
|
3.7.1 A Problem Formulation Template |
|
|
76 | (2) |
|
|
78 | (6) |
|
|
79 | (2) |
|
3.8.1.1 The Complexity Dichotomy |
|
|
79 | (1) |
|
3.8.1.2 Various Definitions of Complexity |
|
|
79 | (1) |
|
3.8.1.3 Partitioning Complexity |
|
|
80 | (1) |
|
|
81 | (1) |
|
|
81 | (3) |
|
3.8.3.1 Resolving the Complexity Dichotomy |
|
|
82 | (2) |
|
3.8.3.2 The Problem Classification Framework |
|
|
84 | (1) |
|
3.9 Remedying Well-Structured Problems |
|
|
84 | (7) |
|
|
85 | (2) |
|
3.9.2 The Multiple-Iteration Problem-Solving Process |
|
|
87 | (3) |
|
3.9.2.1 The First Problem-Solving Processes |
|
|
88 | (1) |
|
3.9.2.2 The Second Problem-Solving Process |
|
|
89 | (1) |
|
3.9.3 A New Product Development Process |
|
|
90 | (1) |
|
3.10 Remedying Ill-Structured Problems |
|
|
91 | (1) |
|
3.11 Remedying Complex Problems |
|
|
91 | (3) |
|
3.11.1 Remedying Well-Structured Complex Problems |
|
|
91 | (1) |
|
3.11.2 Remedying Ill-Structured Complex Problems |
|
|
91 | (2) |
|
3.11.3 Remedying Wicked Problems |
|
|
93 | (1) |
|
|
94 | (1) |
|
|
94 | (3) |
Chapter 4 Management: General and Project Management |
|
97 | (18) |
|
4.1 The Purpose of Management |
|
|
97 | (1) |
|
4.2 Perceptions of Management |
|
|
97 | (4) |
|
|
97 | (1) |
|
|
98 | (1) |
|
|
99 | (1) |
|
|
99 | (2) |
|
4.2.4.1 The Differences between a Manager and a Leader |
|
|
100 | (1) |
|
4.2.4.2 The Difference in Competence |
|
|
100 | (1) |
|
4.2.4.3 The Three Types of Management |
|
|
100 | (1) |
|
4.2.4.4 The Difference between the Requirements for the Project and the Requirements for the Product Produced by the Project |
|
|
100 | (1) |
|
|
101 | (1) |
|
|
101 | (1) |
|
|
101 | (1) |
|
|
101 | (8) |
|
|
102 | (4) |
|
|
102 | (1) |
|
|
102 | (1) |
|
|
103 | (1) |
|
|
103 | (1) |
|
|
103 | (1) |
|
|
103 | (1) |
|
|
103 | (1) |
|
|
104 | (1) |
|
|
104 | (1) |
|
|
104 | (1) |
|
|
104 | (1) |
|
|
105 | (1) |
|
|
106 | (1) |
|
4.4.2 The Triple and Quadruple Constraints of Project Management |
|
|
106 | (1) |
|
4.4.3 Project Organization |
|
|
107 | (2) |
|
4.4.3.1 Project Hierarchy |
|
|
107 | (1) |
|
4.4.3.2 Customer-Project Interfaces |
|
|
108 | (1) |
|
4.5 Taking over a Project |
|
|
109 | (2) |
|
4.5.1 Gain an Understanding of the Situation |
|
|
109 | (1) |
|
4.5.2 Decide If Changes Need to Be Made |
|
|
110 | (1) |
|
4.5.3 Prepare a Change Management Plan |
|
|
110 | (1) |
|
4.5.4 Present the Change Management Plan to the Important Stakeholders |
|
|
111 | (1) |
|
|
111 | (1) |
|
|
111 | (2) |
|
4.6.1 Types of Research Projects |
|
|
111 | (1) |
|
|
112 | (1) |
|
4.6.3 The Need for a Pollinator |
|
|
112 | (1) |
|
|
113 | (1) |
|
|
113 | (2) |
Chapter 5 Project Planning |
|
115 | (80) |
|
5.1 The Project Planning Paradox |
|
|
115 | (1) |
|
5.2 Project Planning and Managing Tools |
|
|
116 | (14) |
|
|
116 | (2) |
|
5.2.1.1 Creating a PAM Chart |
|
|
117 | (1) |
|
|
118 | (3) |
|
5.2.2.1 Creating a Gantt Chart |
|
|
120 | (1) |
|
|
121 | (4) |
|
5.2.3.1 Creating a PERT Chart |
|
|
123 | (2) |
|
|
125 | (1) |
|
5.2.4.1 Creating a Timeline |
|
|
125 | (1) |
|
5.2.5 The GANTT-PERT Cross-Check |
|
|
126 | (1) |
|
|
127 | (3) |
|
5.2.6.1 The Benefits of Using WPs |
|
|
128 | (2) |
|
5.3 The Project Lifecycle |
|
|
130 | (3) |
|
5.3.1 The Four-State Project Lifecycle |
|
|
130 | (3) |
|
5.3.1.1 The Project Initiation State |
|
|
130 | (1) |
|
5.3.1.2 The Project Planning State |
|
|
131 | (1) |
|
5.3.1.3 The Project Performance State |
|
|
131 | (1) |
|
5.3.1.4 The Project Closeout State |
|
|
132 | (1) |
|
|
133 | (9) |
|
5.4.1 The States in the SLC |
|
|
133 | (2) |
|
|
135 | (3) |
|
|
137 | (1) |
|
|
137 | (1) |
|
5.4.3 The Cataract Methodology |
|
|
138 | (4) |
|
|
139 | (3) |
|
|
142 | (1) |
|
|
142 | (5) |
|
5.6.1 Build a Little Test a Little |
|
|
145 | (2) |
|
|
147 | (1) |
|
5.7.1 The Process for Creating a Specific PP |
|
|
147 | (1) |
|
|
147 | (5) |
|
5.8.1 The Numbering System |
|
|
148 | (1) |
|
5.8.2 Process Architecting |
|
|
149 | (6) |
|
|
151 | (1) |
|
5.8.2.2 Common Errors in Developing a WBS |
|
|
152 | (1) |
|
5.9 The Systems Approach to Project Planning |
|
|
152 | (3) |
|
5.10 Using 'Prevention' to Lower Project Completion Risk |
|
|
155 | (1) |
|
5.11 The Presentation Exercise |
|
|
155 | (30) |
|
5.11.1 The Grading Criteria for the Presentation Exercise |
|
|
156 | (1) |
|
5.11.2 The Requirements for the Presentation Exercise |
|
|
156 | (2) |
|
5.11.3 The Presentation Exercise Project Planning State |
|
|
158 | (1) |
|
5.11.4 The Project Numbering System |
|
|
158 | (2) |
|
5.11.4.1 The Activity Categories |
|
|
158 | (1) |
|
5.11.4.2 The Product Categories |
|
|
158 | (1) |
|
5.11.4.3 The Exercise Activities, Products and WPs |
|
|
158 | (2) |
|
5.11.5 The Presentation Planning State (WP 00000) |
|
|
160 | (1) |
|
5.11.6 The Presentation Requirements State (WP 10000) |
|
|
161 | (7) |
|
5.11.7 The Presentation Design State (WP 20000) |
|
|
168 | (1) |
|
5.11.8 The Presentation Construction State (WP 30000) |
|
|
168 | (8) |
|
5.11.9 The Presentation Integration and Testing States (WP 40000) |
|
|
176 | (9) |
|
5.11.10 The Presentation Delivery and Grading State (WP 5000) |
|
|
185 | (1) |
|
5.11.11 Achievements at this Point in Time |
|
|
185 | (1) |
|
5.12 The Engaporean MCSSRP Exercise |
|
|
185 | (7) |
|
5.12.1 The Requirements for the Exercise |
|
|
189 | (3) |
|
|
192 | (1) |
|
|
193 | (2) |
Chapter 6 Successful Project Staffing |
|
195 | (16) |
|
|
195 | (5) |
|
|
195 | (1) |
|
6.1.2 Competencies and Skills |
|
|
195 | (1) |
|
|
196 | (1) |
|
6.1.4 Permanent or Temporary |
|
|
196 | (1) |
|
|
196 | (1) |
|
|
197 | (3) |
|
6.1.6.1 The Lifecycle of a Team |
|
|
197 | (1) |
|
6.1.6.2 Characteristics of Effective Teams |
|
|
198 | (1) |
|
6.1.6.3 Creating and Staffing Effective Teams |
|
|
198 | (2) |
|
6.2 The Systems Approach to Staffing a Team |
|
|
200 | (3) |
|
6.2.1 Breaking Out What Needs to Be Done into Specific Activities in the Three Streams of Work |
|
|
201 | (1) |
|
6.2.2 Determining the Necessary Skills and Competencies to Do the Activities |
|
|
201 | (1) |
|
6.2.3 Partitioning the Activities into Jobs |
|
|
201 | (1) |
|
6.2.4 Staffing Each of the Job Positions |
|
|
202 | (1) |
|
6.3 The Presentation Exercise |
|
|
203 | (6) |
|
6.3.1 Achievements at This Point in Time |
|
|
209 | (1) |
|
6.4 The Engaporean MCSSRP Exercise |
|
|
209 | (1) |
|
6.4.1 Requirements for the Exercise |
|
|
209 | (1) |
|
|
210 | (1) |
|
|
210 | (1) |
Chapter 7 Successful Project Scheduling |
|
211 | (18) |
|
|
211 | (1) |
|
7.2 Estimating the Correct Amount of Time for Activities |
|
|
212 | (1) |
|
7.3 Levelling the Workload |
|
|
213 | (1) |
|
|
214 | (5) |
|
7.4.1 Slack Time, Early and Late Finishes |
|
|
216 | (1) |
|
7.4.2 The Fallacy in the Use of Slack Time in Fixed Resource Situations |
|
|
217 | (1) |
|
7.4.3 Accuracies of the Estimated Schedules |
|
|
218 | (1) |
|
7.5 The Theory of Constraints |
|
|
219 | (1) |
|
|
219 | (2) |
|
7.6.1 Use of the Critical Chain in Project Management |
|
|
220 | (1) |
|
7.7 The Presentation Exercise |
|
|
221 | (5) |
|
7.7.1 Achievements at This Point in Time |
|
|
226 | (1) |
|
7.8 The Engaporean MCSSRP Exercise |
|
|
226 | (1) |
|
7.8.1 The Requirements for the Exercise |
|
|
226 | (1) |
|
|
227 | (1) |
|
|
227 | (2) |
Chapter 8 Successful Project Cost Estimating |
|
229 | (22) |
|
8.1 The Three Axes of Cost-Effective Projects |
|
|
229 | (2) |
|
8.2 The Reason for Estimating Project Costs |
|
|
231 | (1) |
|
8.3 Methods for Estimating Project Costs |
|
|
231 | (7) |
|
8.3.1 Conceptual Design to Cost |
|
|
233 | (3) |
|
8.3.1.1 Benefits of Using CDTC |
|
|
233 | (1) |
|
8.3.1.2 Identifying and Prioritizing the Needed Capability |
|
|
234 | (1) |
|
8.3.1.3 Benchmarking the Capability |
|
|
234 | (1) |
|
8.3.1.4 Determining the Target Price for the Product |
|
|
234 | (1) |
|
8.3.1.5 Estimating the Cost of the Product |
|
|
235 | (1) |
|
8.3.1.6 Adjusting the Cost Estimate |
|
|
236 | (1) |
|
|
236 | (2) |
|
8.3.3 Cost as an Independent Variable |
|
|
238 | (1) |
|
8.4 Accuracies of Cost Estimates |
|
|
238 | (1) |
|
|
239 | (1) |
|
8.6 Ways of Controlling Costs |
|
|
240 | (4) |
|
8.6.1 Failing to Communicate the Vision |
|
|
240 | (1) |
|
8.6.2 Failing to Understand the Customer's Real Requirements |
|
|
241 | (1) |
|
8.6.3 Failing to Plan Ahead |
|
|
241 | (1) |
|
8.6.4 Failing to Control Changes |
|
|
242 | (1) |
|
8.6.5 Failing to Apply Lessons Learned from the Past |
|
|
242 | (1) |
|
8.6.6 Failing to Document the Reasons for Decisions |
|
|
243 | (1) |
|
8.6.7 Failing to Maximize Use of COTS |
|
|
243 | (1) |
|
|
244 | (1) |
|
8.8 The Presentation Exercise |
|
|
244 | (3) |
|
8.8.1 Achievements at This Point in Time |
|
|
246 | (1) |
|
8.9 The Engaporean MCSSRP Exercise |
|
|
247 | (1) |
|
8.9.1 The Requirements for the Exercise |
|
|
247 | (1) |
|
|
248 | (1) |
|
|
248 | (3) |
Chapter 9 Successfully Adjusting Project Schedules and Costs |
|
251 | (16) |
|
9.1 Shortening the Schedule |
|
|
251 | (4) |
|
|
252 | (1) |
|
|
253 | (1) |
|
|
253 | (1) |
|
9.1.4 Improving Productivity |
|
|
254 | (1) |
|
|
255 | (1) |
|
9.2.1 Replacing Personnel Assigned to an Activity with Lower-Cost Personnel |
|
|
255 | (1) |
|
9.2.2 Increasing the Schedule |
|
|
255 | (1) |
|
9.2.3 Deleting Some of the Work without Changing the Requirements |
|
|
256 | (1) |
|
9.2.4 Reducing Materiel Costs |
|
|
256 | (1) |
|
9.2.5 Redesigning the Product |
|
|
256 | (1) |
|
9.2.6 Removing the Low-Priority Requirements |
|
|
256 | (1) |
|
|
256 | (1) |
|
9.4 The Widget System Project |
|
|
257 | (4) |
|
9.4.1 Changes Due to Delays |
|
|
258 | (2) |
|
|
260 | (1) |
|
|
261 | (1) |
|
9.5 The Presentation Exercise |
|
|
261 | (4) |
|
9.5.1 Modifying the Staffing Level |
|
|
261 | (2) |
|
9.5.2 Adjusting the Schedule |
|
|
263 | (1) |
|
9.5.3 Adjusting the Costs |
|
|
263 | (2) |
|
9.6 The Engaporean MCSSRP Exercise |
|
|
265 | (1) |
|
9.6.1 The Requirements for the Exercise |
|
|
265 | (1) |
|
|
266 | (1) |
|
|
266 | (1) |
Chapter 10 An Introduction to Managing Risk and Uncertainty over the Project Lifecyle |
|
267 | (14) |
|
10.1 Definitions of the Terminology |
|
|
267 | (1) |
|
10.2 Risks and Opportunities |
|
|
268 | (1) |
|
10.2.1 The Risk Rectangle |
|
|
268 | (1) |
|
10.2.1.1 The Flaw in the Risk Rectangle |
|
|
269 | (1) |
|
|
269 | (2) |
|
10.3.1 Selected Myths of Risk Management |
|
|
270 | (1) |
|
10.3.2 The Traditional Approach to Risk Management |
|
|
270 | (1) |
|
10.3.3 The Systems Approach to Risk Management |
|
|
271 | (1) |
|
10.4 Risks Based on the Availability of Technology |
|
|
271 | (5) |
|
10.4.1 The Technology Availability Window of Opportunity |
|
|
273 | (3) |
|
|
276 | (1) |
|
10.6 Risk Mitigation or Risk Prevention |
|
|
277 | (1) |
|
|
277 | (1) |
|
10.8 Contingencies and Contingency Plans |
|
|
277 | (1) |
|
10.9 The Engaporean MCSSRP Exercise |
|
|
278 | (1) |
|
10.9.1 The Requirements for the Exercise |
|
|
278 | (1) |
|
|
279 | (1) |
|
|
279 | (2) |
Chapter 11 Successful Performance Monitoring and Controlling |
|
281 | (54) |
|
11.1 Detecting and Preventing Potential Project Overruns |
|
|
282 | (1) |
|
11.2 Ways to Detect Impending Project Failure |
|
|
283 | (3) |
|
11.2.1 The Top Ten Risk-Indicators |
|
|
284 | (1) |
|
11.2.2 The Six Risk-Indicators Most of the Respondents Disagreed |
|
|
285 | (1) |
|
11.3 Managing Changes in Project Scope |
|
|
286 | (2) |
|
11.3.1 Effect of Change on Project |
|
|
286 | (1) |
|
11.3.2 Change Request Processing |
|
|
286 | (2) |
|
|
288 | (11) |
|
11.4.1 The Elements of EVA |
|
|
288 | (1) |
|
11.4.2 The Terminology of EVA |
|
|
289 | (2) |
|
11.4.2.1 Planning or Estimating Terminology |
|
|
289 | (1) |
|
11.4.2.2 Project Monitoring and Controlling Terminology |
|
|
289 | (1) |
|
11.4.2.3 Indices and Summary Terminology |
|
|
289 | (1) |
|
11.4.2.4 EVA Calculations |
|
|
289 | (2) |
|
11.4.3 Requirements for the Use of EVA in a Project |
|
|
291 | (1) |
|
11.4.4 Advantages and Disadvantages of EVA |
|
|
292 | (1) |
|
|
292 | (1) |
|
11.4.4.2 EVA Disadvantages |
|
|
292 | (1) |
|
11.4.5 Examples of the Use of EVA |
|
|
292 | (7) |
|
11.4.5.1 The Master's Degree Project |
|
|
292 | (4) |
|
11.4.5.2 The Data Centre Upgrade Project |
|
|
296 | (3) |
|
11.4.6 The Systems Approach Perspective on EVA |
|
|
299 | (1) |
|
|
299 | (23) |
|
11.5.1 The Five-Step CRIP Approach |
|
|
300 | (2) |
|
11.5.1.1 Step 1: Identify Categories for the Requirements |
|
|
301 | (1) |
|
11.5.1.2 Step 2: Quantify Each Category into Ranges |
|
|
301 | (1) |
|
11.5.1.3 Step 3: Categorize the Requirements |
|
|
302 | (1) |
|
11.5.1.4 Step 4: Place Each Requirement into a Range in Each Category |
|
|
302 | (1) |
|
11.5.1.5 Step 5: States of Implementation |
|
|
302 | (1) |
|
11.5.2 Populating and Using the CRIP Chart |
|
|
302 | (3) |
|
11.5.3 Advantages of the CRIP Approach |
|
|
305 | (1) |
|
11.5.4 Disadvantages of the CRIP Approach |
|
|
305 | (1) |
|
11.5.5 Examples of Using CRIP Charts in Different Types of Projects |
|
|
305 | (17) |
|
11.5.5.1 The Ideal Project |
|
|
309 | (4) |
|
11.5.5.2 A Project with Requirements Creep |
|
|
313 | (5) |
|
11.5.5.3 The Challenged Project |
|
|
318 | (1) |
|
11.5.5.4 The 'Make Up Your Mind' Project |
|
|
319 | (3) |
|
|
322 | (1) |
|
11.6 Traffic Light and ETL Charts |
|
|
322 | (7) |
|
11.6.1 Traffic Light Charts |
|
|
322 | (1) |
|
|
323 | (6) |
|
11.6.2.1 Creating an ETL Chart for Use in a Presentation |
|
|
328 | (1) |
|
11.6.2.2 Adding Even More Information |
|
|
328 | (1) |
|
|
329 | (1) |
|
11.7.1 MBO in the Planning State of a Project |
|
|
330 | (1) |
|
|
330 | (2) |
|
11.8.1 The Key Ingredients in MBE |
|
|
330 | (1) |
|
11.8.2 Advantages and Disadvantages of MBE |
|
|
331 | (1) |
|
|
331 | (1) |
|
11.9 The Engaporean MCSSRP Exercise |
|
|
332 | (1) |
|
11.9.1 The Requirements for the Exercise |
|
|
332 | (1) |
|
|
332 | (1) |
|
|
332 | (3) |
Chapter 12 The Human Element |
|
335 | (18) |
|
|
335 | (1) |
|
|
336 | (3) |
|
12.2.1 Rewards and Recognition |
|
|
336 | (3) |
|
12.2.1.1 Performance Evaluations |
|
|
336 | (3) |
|
|
339 | (2) |
|
12.3.1 Basis for Conflict |
|
|
340 | (1) |
|
12.3.2 Response to Conflict |
|
|
340 | (1) |
|
12.3.2.1 Gaining an Understanding of the Situation |
|
|
340 | (1) |
|
12.3.3 Perceptions of Conflict |
|
|
340 | (1) |
|
|
341 | (5) |
|
12.4.1 Types of Power and Influence |
|
|
342 | (1) |
|
12.4.2 Types of Authority |
|
|
343 | (1) |
|
|
343 | (3) |
|
|
343 | (1) |
|
|
343 | (1) |
|
|
344 | (1) |
|
|
344 | (1) |
|
|
344 | (1) |
|
|
345 | (1) |
|
|
346 | (2) |
|
12.5.1 Negotiation Positions |
|
|
346 | (1) |
|
12.5.2 Negotiation Outcomes |
|
|
346 | (1) |
|
12.5.3 Negotiating Styles |
|
|
347 | (1) |
|
|
347 | (1) |
|
12.6 Managing Stakeholders |
|
|
348 | (2) |
|
12.7 The Multi-satellite Communications Switching System Replacement Project Exercise |
|
|
350 | (1) |
|
12.7.1 The Requirements for the Exercise |
|
|
350 | (1) |
|
|
351 | (1) |
|
|
351 | (2) |
Chapter 13 Ethics |
|
353 | (14) |
|
|
353 | (1) |
|
13.2 Organizational Ethics |
|
|
354 | (1) |
|
|
354 | (1) |
|
|
354 | (1) |
|
|
355 | (7) |
|
|
355 | (2) |
|
|
355 | (1) |
|
|
356 | (1) |
|
13.5.1.3 The Company's Ethics Policy |
|
|
356 | (1) |
|
13.5.1.4 The Consequences of Your Actions |
|
|
357 | (1) |
|
13.5.2 The Approach to Solving the Ethical Problem |
|
|
357 | (6) |
|
13.5.2.1 Analyse the Situation |
|
|
358 | (1) |
|
13.5.2.2 Identify Appropriate Lessons Learned |
|
|
358 | (1) |
|
13.5.2.3 Develop Alternatives |
|
|
358 | (1) |
|
13.5.2.4 Determine the Probable Outcome of Each Alternative Decision |
|
|
358 | (1) |
|
13.5.2.5 Evaluate the Alternatives |
|
|
359 | (1) |
|
|
360 | (2) |
|
|
362 | (1) |
|
13.7 The Multi-satellite Communications Switching System Replacement Project Exercise |
|
|
363 | (1) |
|
13.7.1 The Requirements for the Exercise |
|
|
363 | (1) |
|
|
364 | (1) |
|
|
364 | (3) |
Appendix 1: The Engaporian Multi-satellite Operations Control Centre Communications Switching System Replacement Project |
|
367 | (2) |
Appendix 2: Change Management Events |
|
369 | (2) |
Appendix 3: Presentation Guidelines and Requirements |
|
371 | (2) |
Appendix 4: Staffing Information |
|
373 | (2) |
Appendix 5: Resumes for the Session 6 Exercise |
|
375 | (18) |
Author Index |
|
393 | (4) |
Subject Index |
|
397 | |