Abbreviations |
|
xiv | |
Preface |
|
xv | |
|
|
1 | (16) |
|
|
1 | (1) |
|
|
2 | (5) |
|
|
2 | (1) |
|
|
2 | (1) |
|
|
3 | (1) |
|
|
4 | (1) |
|
Time and Money Complications |
|
|
5 | (1) |
|
Do the Triple Constraints Sufficiently Define a Project? |
|
|
5 | (1) |
|
|
6 | (1) |
|
|
6 | (1) |
|
Comprised of and Breakable to Tasks |
|
|
7 | (1) |
|
|
7 | (1) |
|
Other Requirements and/or Expectations |
|
|
7 | (1) |
|
Can Value Be a Project Definer? |
|
|
8 | (1) |
|
What Happens If It Is Not a "Project"? |
|
|
8 | (1) |
|
|
9 | (7) |
|
Types of Construction Projects |
|
|
9 | (1) |
|
Public and Private Construction Projects |
|
|
9 | (2) |
|
Buildings: Residential and Nonresidential Building Projects |
|
|
11 | (1) |
|
Heavy and Civil Engineering Construction Projects |
|
|
11 | (1) |
|
Stakeholders and Key Participants |
|
|
11 | (1) |
|
Stakeholders' Differing Project Perspectives |
|
|
12 | (1) |
|
Basic Functions of the Stakeholders |
|
|
12 | (1) |
|
The Operator as the Fourth Stakeholder |
|
|
13 | (1) |
|
|
14 | (1) |
|
Most Common Project Delivery Systems |
|
|
14 | (1) |
|
Construction Contract Pricing Options |
|
|
15 | (1) |
|
|
15 | (1) |
|
|
15 | (1) |
|
Variations of Cost Plus Fee Contracts |
|
|
16 | (1) |
|
|
16 | (1) |
|
2 Management, Project Management, and Construction Projects |
|
|
17 | (21) |
|
|
17 | (1) |
|
|
17 | (5) |
|
|
18 | (1) |
|
|
19 | (1) |
|
Everybody Manages Something |
|
|
19 | (1) |
|
|
19 | (1) |
|
|
20 | (1) |
|
Management Levels and Titles |
|
|
20 | (1) |
|
Accountability and Dependency |
|
|
20 | (2) |
|
Roots of Modem Management |
|
|
22 | (4) |
|
|
26 | (1) |
|
|
26 | (1) |
|
|
26 | (1) |
|
|
26 | (1) |
|
|
26 | (2) |
|
|
27 | (1) |
|
Interpersonal (Human) Skills |
|
|
27 | (1) |
|
|
27 | (1) |
|
|
28 | (1) |
|
Managers Have to Make Decisions |
|
|
28 | (2) |
|
Common Decision-Making Mistakes |
|
|
30 | (1) |
|
|
30 | (3) |
|
|
30 | (2) |
|
|
32 | (1) |
|
|
32 | (1) |
|
|
33 | (1) |
|
Most Common Managerial Mistakes |
|
|
33 | (1) |
|
|
33 | (2) |
|
Construction Project Management |
|
|
35 | (1) |
|
Cost and Time Considerations at Initial Stages of a Construction Project |
|
|
35 | (1) |
|
|
36 | (2) |
|
3 Understanding Cost and Its Elements |
|
|
38 | (17) |
|
|
38 | (1) |
|
Cost Is More Than a Dollar Amount |
|
|
38 | (2) |
|
|
40 | (2) |
|
|
42 | (1) |
|
|
42 | (1) |
|
|
43 | (1) |
|
|
43 | (1) |
|
Example for Unit Cost Conversions, Assembly Unit Cost, and Performance Assumptions |
|
|
43 | (7) |
|
Unit Cost Conversion for Materials |
|
|
44 | (1) |
|
|
44 | (1) |
|
|
45 | (1) |
|
|
46 | (1) |
|
Resource (Labor or M/E)- Hours |
|
|
47 | (1) |
|
Output Rates, Resource-Hours and Activity Durations |
|
|
47 | (3) |
|
Managing a Cost Requires Knowing Both of Its Elements |
|
|
50 | (1) |
|
|
50 | (1) |
|
Can the Price Be Less Than Its Cost? |
|
|
51 | (1) |
|
|
51 | (3) |
|
|
52 | (1) |
|
|
53 | (1) |
|
Value Priorities of Stakeholders and Key Participants |
|
|
53 | (1) |
|
Value as a Measure of Project Success |
|
|
54 | (1) |
|
Considerations for Setting Value Goals for Projects |
|
|
54 | (1) |
|
|
54 | (1) |
|
4 Cost Types and Components |
|
|
55 | (14) |
|
|
55 | (1) |
|
|
55 | (7) |
|
Direct and Indirect Costs |
|
|
55 | (2) |
|
|
57 | (1) |
|
|
57 | (1) |
|
|
57 | (1) |
|
|
57 | (1) |
|
|
58 | (1) |
|
|
58 | (1) |
|
Identifying Cost Types Example |
|
|
58 | (4) |
|
|
62 | (4) |
|
|
62 | (1) |
|
|
62 | (2) |
|
Machinery, Equipment, and Other Direct Costs (M/E) Component |
|
|
64 | (1) |
|
|
64 | (2) |
|
Depreciation Is Not a Cost |
|
|
66 | (1) |
|
What Do Cost Types and Components Indicate? |
|
|
67 | (1) |
|
|
67 | (2) |
|
5 Structuring Project Cost |
|
|
69 | (16) |
|
|
69 | (1) |
|
|
69 | (6) |
|
Initiator of the Project Planning Process: Scope |
|
|
71 | (1) |
|
Detailing Scope by Breaking It Down to Tasks: Work Breakdown Structure (WBS) |
|
|
72 | (1) |
|
WBS Should Cover the Entire Scope |
|
|
73 | (1) |
|
Example: Dinner Party Project |
|
|
73 | (2) |
|
Compiling Detailed Task Information: Work Package Dictionary (WPD) |
|
|
75 | (1) |
|
Structured Project Cost: Project Cost Breakdown (PCB) |
|
|
76 | (4) |
|
PCB and Project Price Breakdown |
|
|
80 | (1) |
|
Different Perspectives for PCB |
|
|
80 | (3) |
|
WBS Examples for Different Stakeholders |
|
|
83 | (1) |
|
|
83 | (2) |
|
|
85 | (23) |
|
|
85 | (1) |
|
Cost Estimating in the Construction Industry |
|
|
85 | (1) |
|
Types of Estimates and Estimate Accuracies |
|
|
86 | (2) |
|
Cost Estimating Process for Line Items |
|
|
88 | (2) |
|
|
89 | (1) |
|
|
89 | (1) |
|
Labor and M/E QTOs and Durations |
|
|
89 | (1) |
|
Estimate Preparation Duration and Accuracy |
|
|
90 | (1) |
|
Expert Opinion in Estimating Costs |
|
|
91 | (1) |
|
Step-by-Step Cost Estimating Process |
|
|
91 | (2) |
|
Project Delivery Systems, Contract Pricing, and Cost Estimating |
|
|
93 | (1) |
|
Technology and Reference Data for Estimating |
|
|
94 | (1) |
|
Updating WPD With Estimated Cost Data |
|
|
95 | (1) |
|
WPD and Project Resource Schedule (RBOQ) |
|
|
95 | (2) |
|
Example: Hotel Building Superstructure |
|
|
97 | (8) |
|
Quantity Take-Offs, BOQ, WPD Update, and Project Resource BOQ |
|
|
97 | (1) |
|
Step 1 Prepare (or Check if Available) Quantity Take-Offs |
|
|
97 | (1) |
|
Step 2 Update the WPD for This Activity |
|
|
97 | (1) |
|
Step 3 Assign Resources and Determine Durations |
|
|
97 | (3) |
|
Step 4 Calculate the Cost by Applying Unit Costs to the Quantities |
|
|
100 | (1) |
|
Step 5 Check Cost and Schedule Acceptability |
|
|
100 | (3) |
|
Option 1 Increasing Crew Size |
|
|
103 | (1) |
|
Option 2 Keeping the Initial Crew Size and Paying Overtime as Needed |
|
|
104 | (1) |
|
|
105 | (1) |
|
Step 6 Finalize by Updating WPD |
|
|
105 | (1) |
|
Remarks on Cost and Duration Correlation for the Example |
|
|
105 | (1) |
|
|
105 | (2) |
|
|
106 | (1) |
|
|
106 | (1) |
|
|
106 | (1) |
|
|
106 | (1) |
|
|
107 | (1) |
|
7 Contingency as a Part of Cost |
|
|
108 | (12) |
|
|
108 | (1) |
|
Certainty, Uncertainty, Risk, and Contingency |
|
|
108 | (3) |
|
The Known and Unknown Risks |
|
|
109 | (1) |
|
|
109 | (1) |
|
|
110 | (1) |
|
Contingency at Several WBS Levels |
|
|
111 | (1) |
|
Both Cost Elements May Include Contingencies |
|
|
111 | (1) |
|
Typical Uses of Contingencies |
|
|
112 | (1) |
|
|
112 | (1) |
|
|
112 | (1) |
|
|
112 | (1) |
|
|
113 | (1) |
|
|
113 | (1) |
|
Using a Provisional Sum to Avoid a Contingency |
|
|
114 | (1) |
|
Dealing With Unknown-Unknown Scope Changes |
|
|
114 | (1) |
|
|
115 | (2) |
|
Contingency and Change Orders |
|
|
117 | (1) |
|
|
117 | (1) |
|
|
118 | (1) |
|
Management Reserve and Project Manager |
|
|
118 | (1) |
|
|
119 | (1) |
|
|
120 | (19) |
|
|
120 | (1) |
|
Project and Operational Budgets |
|
|
120 | (1) |
|
One-Time Occurring and Not Repetitive |
|
|
120 | (1) |
|
Covers the Entire Project Duration |
|
|
121 | (1) |
|
Requires Unique and Project-Specific Resources |
|
|
121 | (1) |
|
Project Cost Budget Includes and Reveals All Required Resources |
|
|
121 | (1) |
|
Project Cost Budgets and Schedules Are Interrelated |
|
|
121 | (1) |
|
Project Budgets Include All Known-Unknowns |
|
|
122 | (1) |
|
Preparing and Reporting Cost Budgets |
|
|
122 | (2) |
|
|
122 | (1) |
|
|
123 | (1) |
|
Budgeting for Project Resources |
|
|
124 | (1) |
|
|
124 | (1) |
|
|
124 | (7) |
|
Budget Format for Performance Monitoring |
|
|
126 | (1) |
|
Budget Format for Futuristic Projections |
|
|
126 | (3) |
|
Monitoring Project Resources and Output Rates |
|
|
129 | (2) |
|
|
131 | (4) |
|
Budget--Schedule Integration: Expense Flows and Resource Schedules |
|
|
135 | (2) |
|
|
137 | (1) |
|
|
138 | (1) |
|
|
139 | (32) |
|
|
139 | (1) |
|
Cost Accounting Versus Cost Control |
|
|
140 | (2) |
|
|
140 | (1) |
|
Accrued Expense Versus Committed Cost |
|
|
141 | (1) |
|
Step-by-Step Cost Controlling Process |
|
|
142 | (2) |
|
Cost Control Is Not a Process of Reducing Cost |
|
|
144 | (1) |
|
|
144 | (8) |
|
|
145 | (4) |
|
|
149 | (1) |
|
|
149 | (1) |
|
|
150 | (1) |
|
|
150 | (1) |
|
|
151 | (1) |
|
Processing Progress, Invoices, and Payroll |
|
|
152 | (1) |
|
Sorting and Distributing Accounting Cost Data |
|
|
152 | (1) |
|
Calculating/Verifying Actual Quantities |
|
|
152 | (1) |
|
Interpreting Monitored Performance |
|
|
152 | (2) |
|
|
154 | (6) |
|
Common Reasons for Quantity Variance |
|
|
155 | (1) |
|
|
155 | (1) |
|
|
155 | (1) |
|
|
155 | (1) |
|
|
156 | (1) |
|
|
156 | (1) |
|
|
156 | (1) |
|
|
157 | (1) |
|
|
157 | (1) |
|
|
157 | (1) |
|
Differing/Unforeseen Site Conditions |
|
|
158 | (1) |
|
|
158 | (1) |
|
|
158 | (1) |
|
|
158 | (1) |
|
Errors, Inflation, Changes, Market, and Adverse Conditions |
|
|
158 | (1) |
|
Unit Cost Variance and Quantity Implications |
|
|
159 | (1) |
|
Labor and M/E Performance Variances |
|
|
159 | (1) |
|
Remedial Action Considerations |
|
|
160 | (4) |
|
Variance Accountability and Remedial Action |
|
|
161 | (1) |
|
Categorical Remedial Action Options |
|
|
162 | (2) |
|
Remedial Action and Delivery Method/Contract Pricing Complications |
|
|
164 | (2) |
|
What Is the Right Remedial Action? |
|
|
166 | (1) |
|
Implementing Remedial Actions |
|
|
166 | (2) |
|
|
167 | (1) |
|
Disputes Related to Variances |
|
|
168 | (1) |
|
Cost Control Process Schematics |
|
|
168 | (2) |
|
|
170 | (1) |
|
|
171 | (21) |
|
Appendix A Cost Budget Forms for Hotel Project Stakeholders |
|
|
172 | (13) |
|
|
173 | (4) |
|
|
177 | (4) |
|
|
181 | (2) |
|
|
183 | (2) |
|
Appendix B Sample Work Package Dictionary Form |
|
|
185 | (2) |
|
Appendix C Typical Progress Report Forms |
|
|
187 | (5) |
|
|
187 | (1) |
|
|
188 | (4) |
About the Author |
|
192 | (1) |
Index |
|
193 | |