Muutke küpsiste eelistusi

Law of Construction Disputes [Kõva köide]

(Crown Office Chambers, UK)
  • Formaat: Hardback, 678 pages, kõrgus x laius: 244x169 mm, kaal: 1302 g
  • Sari: Construction Practice Series
  • Ilmumisaeg: 01-Jul-2010
  • Kirjastus: Informa Law
  • ISBN-10: 1843119013
  • ISBN-13: 9781843119012
  • Kõva köide
  • Hind: 408,25 €*
  • * saadame teile pakkumise kasutatud raamatule, mille hind võib erineda kodulehel olevast hinnast
  • See raamat on trükist otsas, kuid me saadame teile pakkumise kasutatud raamatule.
  • Kogus:
  • Lisa ostukorvi
  • Tasuta tarne
  • Lisa soovinimekirja
  • Formaat: Hardback, 678 pages, kõrgus x laius: 244x169 mm, kaal: 1302 g
  • Sari: Construction Practice Series
  • Ilmumisaeg: 01-Jul-2010
  • Kirjastus: Informa Law
  • ISBN-10: 1843119013
  • ISBN-13: 9781843119012
The Law of Construction Disputes covers the construction dispute process by analysing the main areas that can lead to disputes and how to effectively deal with them once they have arisen. The book combines theory and practice along with exact excerpts of the leading case decisions covering the entire spectrum of construction law and the disputes that arise. “It should not be thought of a book that is only to be taken to and used at a hearing in case it is needed. It should be read thoroughly in any preparatory phase as it provides a good survey of the law and practice key and so that the many additional references, e.g., in the foot notes, can be pursued.” Humphrey Lloyd, International Construction Law Review [ 2011] ICLR 130

Arvustused

"It should not be thought of a book that is only to be taken to and used at a hearing in case it is needed. It should be read thoroughly in any preparatory phase as it provides a good survey of the law and practice key and so that the many additional references, e.g., in the foot notes, can be pursued. Humphrey Lloyd, International Construction Law Review [ 2011] ICLR 130

The Author v
Preface vii
Acknowledgements ix
Table of Cases
xix
Table of Legislation
xxxi
1 Introduction to Construction Disputes
Applicable Principles of Law
1(1)
Common Law
1(5)
History
1(4)
Common Law Countries
5(1)
Civil Law
6(3)
The Napoleonic Code
7(2)
Differences Between Common and Civil Law
9(1)
Sharia - Islamic Law
9(8)
History
10(4)
Enforcement of Adjudication Decisions v Arbitration Awards
14(3)
The Historical Development of Dispute Resolution in Construction Matters
17(2)
The Legal Development of Other Dispute Resolution Methods
19(5)
The Engineer/Arbitrator as Judge
20(2)
The Engineer as Quasi-Arbitrator
22(2)
The Development of Non-statutory Adjudication
24(10)
The Advent of Dispute Boards in England
26(1)
Extension to International Cases
27(4)
Specific Regional Differences and Methods
31(3)
Forms of Standard Construction Contracts
34(5)
Use of Form Contracts
35(1)
Methods of Construction Contracting
36(3)
Contractual Operational and Payment Formats
39(2)
The Traditional Lump Sum or Fixed Price Contract
39(1)
The Guaranteed Maximum Price Contract
39(1)
The Remeasurement Type of Contract
39(1)
The Cost Reimbursement or Cost Plus Fee Contract
40(1)
Target Cost Contracts
40(1)
2 The Construction Contract
Formation
41(9)
Defining a Contract
41(1)
Offer and Acceptance
42(2)
Implied Agreements
44(1)
Capacity
44(1)
Consideration
45(2)
Intent to be Legally Bound
47(1)
Privity of Contract
47(1)
Oral Contracts
48(1)
Letters of Intent
49(1)
Other Contract Issues
50(1)
Battle of the Forms and Related Difficulties
50(2)
The Construction Tender
52(4)
Unilateral v Bilateral Contracts
56(1)
Uncertainity
56(1)
Conditions as Terms of a Contract
57(1)
Terms which are Implied
57(1)
Terms Implied in Fact
57(1)
Misrepresentation
58(17)
Distinctions
60(1)
Express False Representations
61(1)
Implied Misrepresentations
62(1)
Negligent Misreprentations
62(1)
Innocent Misrepresentations
63(1)
Misstatements of the Law v Fact
63(1)
Mistake
64(1)
Unilateral Mistake
64(2)
Mutual Mistake
66(1)
Common Mistake
67(3)
Mistake v Frustration v Impossibility
70(5)
3 Areas of Dispute and Liability
Design Professionals
75(32)
The Design Professional: Architect/Engineer's Duty---Tort-v-Contract
77(1)
Fitness for Purpose Liability
78(2)
Reasonable Skill and Care
80(1)
Concurrent Negligence and Contract Duty
81(11)
Duty to Warn of Retrospective Danger
92(5)
Duty to Others
97(1)
Purely Economic Losses
97(1)
Miscellaneous Matters: Personal Injury, Latent Defects, and Subsequent Occupiers
98(2)
Other Issues
100(3)
The Knowledge of Others
103(1)
Matters Other Than Design
104(1)
New, Novel and Striet Design Standards
104(2)
Liability for Design of Others
106(1)
4 Site Conditions
The Site
107(6)
Right to Access
107(1)
Possession by Whom?
108(1)
Does the Contractor have a License to Enter the Site?
109(4)
Access and Possession
113(12)
Site Access after Completion
114(1)
Site Conditions
114(1)
Unforeseen Ground Conditions
115(3)
Contract Provisions for Unexpected Ground Conditions
118(1)
Misrepresentation of the Site Conditions
119(2)
The Site Under the Housing Grants Act
121(1)
Employer Responsibility Regarding Possession
122(3)
5 The Subcontractor
Types of Subcontracts
125(2)
Relations with Contractor
125(1)
Employer Insolvency and Payments
126(1)
Default by Subcontractor
127(8)
Delay Issues
127(2)
Defect Issues
129(2)
Problems with Nominated Subcontractors
131(4)
Relations with Employer
135(1)
No Privity
135(1)
The Contracts (Rights of Third Parties) Act 1999
136(3)
Liability in Tort
136(1)
Relations with Architect and Engineer
137(2)
6 Defences to Construction Disputes
Force Majeure
139(9)
Is the Contracted Terminated?
141(1)
Acts of God
142(1)
The Purpose of Force Majeure Clauses---Historically and Internationally
143(1)
Typical Force Majeure Clause Usage
144(1)
The Necessary Requirements for Force Majeure
145(1)
When Does Force Majeure Commence
146(1)
The Duration of the Condition
146(1)
When Should Notice be Given
147(1)
Force Majeure's Effect
147(1)
Frustration
148(6)
7 Issues Regarding Contractors Rights and Obligations Under Standard Form Agreements
Design and Build Form Contracts
154(10)
Particular Provisions such as Extension of Time Clauses
156(1)
EOT "Sweeping-Up" Clauses
157(1)
The Other Major Forms of Contract
157(1)
The JCT Forms of Contract
157(2)
JCT 98 Standard Form of Building Contract (JCT 98 SFBC)
159(1)
The Changes Made in the SBC05
160(2)
Payment
162(1)
Insurance Issues
162(1)
Commencement, Progress and Completion
163(1)
Warranties/Third Party Rights
163(1)
Termination
164(1)
Dispute Resolution
164(1)
The Ice Conditions of Contract
164(7)
Measurment Version 7th Edition
165(1)
ICE Design and Construct Contract
165(1)
ICE Minor Works Contract
165(1)
Time and Cost Issues Under the Measurement Version, Design and Construct, Minor Works
165(2)
The NEC3---The New Engineering Contract Engineering and Construction Contract --- NEC ECC
167(1)
Overview
167(1)
Some Important Provisions
168(1)
Prevention Clause 19
169(1)
The Concept of Key Dates
170(1)
Design Liability
170(1)
Payment for Defective Work
170(1)
The Fidic Forms of Contract
171(1)
The Three Main FIDIC Forms of Contract
171(1)
The Proper Form
171(1)
Employer Design of the Project
171(1)
Contractor Design of the Project
171(1)
Common Issues between the Forms
172(4)
The Role of the Engineer
172(1)
Contractor Incentives
173(1)
Variations
173(1)
Contractor's Rights and Obligations
174(1)
Additional Obligations and Issues
175(1)
Termination Issues
175(1)
Force Majeure
176(1)
Unforeseen Conditions
176(3)
The Red and Yellow Books
176(1)
The Silver Book
177(1)
Damages
177(2)
8 Termination of Contract
Termination v Determination
179(18)
Common Law Repudiation v Determination
184(1)
Can Suspension be Repudiation?
185(1)
Anticipatory Repudiation
186(1)
A Repudiation Need Not be Accepted
187(2)
Rescission
189(1)
Release
190(2)
Accord and Satisfaction
192(1)
Waiver and Promissory Estoppel
193(4)
9 The Certification Process
Certificates
197(5)
Certificate Requirements
199(1)
Errors
199(1)
Interim Certificates
200(1)
Impartiality of the Certifier
201(1)
Certifier Liability
202(9)
History
202(9)
Variations
211(15)
Is it a Variation or a Separate Contract?
211(5)
Implied Variations
216(1)
Ordering Variations
216(1)
Failure to Order a Variation
217(1)
Removing Work
218(3)
What is the Basis for Payment and Value of the Variation?
221(2)
Value
223(2)
Standard Methods of Measurement
225(1)
Errors
226(1)
Final Certificates
226(1)
Final Account Statements
226(5)
10 Types of Claims
Claims for Money
231(47)
The Issue of Causation
232(5)
Contribution
237(3)
Money Damages but at What Cost
240(3)
Reasonableness
243(3)
Contract v Tort Damages
246(4)
Claims for Performance
250(1)
Liquidated Damages and Claims for Extensions of Time
251(6)
Delay v Disruption
257(1)
Extensions of Time
258(2)
The Standard Forms
260(1)
Who Determines the Extension
261(1)
Float
262(2)
Concurrent Delay
264(2)
Diminution in Value
266(5)
Abatement v Set-Off
271(7)
11 Collateral Warranties
Collateral Warranty Provisions
278(7)
The Contracts (Rights of Third Parties) Act 1999
279(1)
Enforcing Variation and Rescission of Contract
280(1)
Defences
281(1)
The Promisee's Enforcement of the Contract
282(1)
Opting out of the Act
283(2)
12 Non-Contract Liability
Negligence
285(28)
The "Threefold Test"
301(1)
The "Assumption of Responsibility Test"
301(1)
The "Incremental Test"
301(1)
The "Holistic Test"
302(1)
Vicarious Liability
303(5)
Nuisance
308(1)
Limiting Factors
309(1)
Strict Liability in Nuisance---The Rule in Rylands v Fletcher
309(2)
Trespass v Nuisance
311(1)
Encroachment
312(1)
13 Time at Large and Time Bar Clauses
Time at Large
313(9)
Time Barred Claims
322(9)
14 Dispute Resolution
Conventional Model
331(3)
Litigation v Arbitration v Mediation
333(1)
Arbitration
334(2)
The Arbitration Act 1996
335(1)
The Arbitration Process
335(1)
The Arbitrator
336(2)
The Award
337(1)
Arbitration Variations
337(1)
Mediation During the Litigation/Arbitration Process
337(1)
Refusing to Mediate
338(6)
Enforceability of ADR Agreements and Mediation Settlement Agreements
341(1)
Withdrawing from Mediation
342(1)
Refusing to Mediate --- No Cost Consequences
342(1)
Adjudication
343(1)
Mandatory Provisions
344(6)
The Process Under the Act
344(1)
The Scheme for Construction Contracts
345(1)
The Act's Main Areas---Is There a Dispute?
346(2)
Does the Dispute Arise Under a Construction Contract?
348(1)
Is the Contract In Writing Within the Meaning of Section 107?
349(1)
The Process
350(7)
Procedures under the Scheme
353(1)
Notice of Adjudication
353(1)
Appointment of an Adjudicator
353(1)
The Referral Notice
354(1)
Adjudicator's Powers and Duties
354(1)
Changes to the Housing Grants Act
355(2)
Dispute Boards
357(6)
What is a Dispute Board?
358(1)
What makes a Dispute Board unique?-What can be achieved by using a Dispute Board?
359(1)
Non-Binding Recommendations
360(1)
Interim Binding Decisions
361(1)
History of Dispute Boards
362(1)
The World Bank
363(10)
Harmonised Contract Conditions
363(1)
Growth of Dispute Boards
364(1)
An Overview---Composition of Dispute Boards and Their Operation
365(1)
Appointment and Membership
365(1)
The Importance of Early Appointment and of Regular Site Visits
366(1)
Routine Operations
367(1)
Informal Operations
368(1)
Dispute Board Procedures
368(1)
Dispute Review Board Costs
369(1)
Why Dispute Boards Work
370(1)
International Aspects
371(2)
15 Key Issues in Dispute Resolution
Agreements
373(11)
Disclosure
382(2)
E-Disclosure
384(9)
The Chartered Institute of Arbitrators Protocol for E-disclosure in Arbitration
387(2)
Confidentiality
389(1)
Enforcement of Foreign Awards in the UK
390(3)
Serial Adjudication Decisions
393(11)
Adjudication Conundrum
393(1)
Election
394(8)
Set-off
402(2)
Arbitration of Dispute Board Decisions
404(1)
Notice of Dissatisfaction
405(1)
Amicable Settlement
405(1)
Arbitration
405(8)
APPENDICES
1 Glossary of Construction Terms
413(18)
2 Housing Grants, Construction and Regeneration Act 1996
431(10)
3 The Scheme for Construction Contracts (England and Wales) Regulations 1998
441(12)
4 Contracts (Rights of Third Parties) Act 1999
453(8)
5 Dispute Board Provisions Under the FIDIC Red Book
461(14)
6 Dispute Board Provisions Under the FIDIC Yellow Book
475(12)
7 Dispute Board Provisions Under the FIDIC Silver Book
487(12)
8 ICC Dispute Board Rules
499(20)
9 The Dispute Board Federation Dispute Adjudication Board Ad Hoc DAB Rules
519(12)
10 The Defective Premises Act 1972
531(6)
11 Unfair Contract Terms Act 1977
537(8)
12 Torts (Interference with Goods) Act 1977
545(8)
13 Sale of Goods Act 1979
553(20)
14 Limitations Act 1980
573(30)
15 Supply of Goods and Services Act 1982
603(20)
16 Latent Damage Act 1986
623(6)
Index 629
Dr Chern is a Barrister practising at Crown Office Chambers, London. He has practised since 1972 specifically in the areas of engineering and construction disputes in the United Kingdom, the EU and internationally.