Preface |
|
ix | |
About the author |
|
xi | |
|
|
xiii | |
|
|
1 | (4) |
|
02 What is the role of Defined Cost in NEC4 contracts? |
|
|
5 | (4) |
|
03 What is a compensation event? |
|
|
9 | (6) |
|
|
9 | (1) |
|
|
9 | (1) |
|
What is a compensation event? |
|
|
10 | (1) |
|
Administering compensation events |
|
|
11 | (1) |
|
Are compensation events just in clause 60.1? |
|
|
12 | (3) |
|
04 Compensation events 60.1(1)-60.1(10) |
|
|
15 | (12) |
|
05 Compensation events 60.1(11)-60.1(21) |
|
|
27 | (10) |
|
06 Compensation events in the main and secondary Options |
|
|
37 | (6) |
|
07 Notifying compensation events, producing quotations and proposed instructions |
|
|
43 | (16) |
|
Compensation event processes |
|
|
43 | (1) |
|
|
44 | (2) |
|
|
46 | (2) |
|
|
48 | (5) |
|
|
53 | (6) |
|
08 Assessing and implementing compensation events |
|
|
59 | (10) |
|
The Project Manager's assessments |
|
|
64 | (2) |
|
Implementing compensation events |
|
|
66 | (3) |
|
09 Time assessments of compensation events |
|
|
69 | (8) |
|
Time assessments in this book |
|
|
69 | (1) |
|
Time obligations in contracts generally |
|
|
69 | (1) |
|
Time obligations in the ECC |
|
|
70 | (1) |
|
|
70 | (1) |
|
Shared principles in the assessment of time and money |
|
|
71 | (1) |
|
How is the delay calculated? |
|
|
71 | (1) |
|
The additional clauses that link to clause 63.5 |
|
|
72 | (5) |
|
|
77 | (6) |
|
11 Defined Cost and assessing compensation events in main Option A and B contracts and the Short Schedule of Cost Components |
|
|
83 | (22) |
|
Defined Cost in main Option A and B contracts |
|
|
83 | (1) |
|
Assessment of compensation events in main Option A and B contracts |
|
|
83 | (7) |
|
The Short Schedule of Cost Components |
|
|
90 | (15) |
|
12 Defined Cost in main Option C, D and E contracts. Disallowed Cost and the Schedule of Cost Components |
|
|
105 | (20) |
|
Defined cost in main Option C, D and E contracts |
|
|
105 | (1) |
|
|
106 | (2) |
|
Schedule of Cost Components |
|
|
108 | (17) |
|
13 Main Option C, D and E contracts: assessment of Price for Work Done to Date and assessment of compensation events |
|
|
125 | (10) |
|
Assessment of Price for Work Done to Date |
|
|
125 | (3) |
|
Assessment of compensation events |
|
|
128 | (7) |
|
14 Main Option F contracts: Defined Cost, Disallowed Cost, assessment of Price for Work Done to Date and assessment of compensation events |
|
|
135 | (10) |
|
The role of Defined Cost in main Option F contracts |
|
|
135 | (1) |
|
Defined Cost in main Option F contracts |
|
|
136 | (1) |
|
Disallowed Cost in main Option F contracts |
|
|
136 | (2) |
|
The Price for Work Done to Date in main Option F contracts |
|
|
138 | (3) |
|
Assessment of compensation events in main Option F contracts |
|
|
141 | (4) |
|
|
145 | (4) |
|
Finalising costs generally |
|
|
145 | (1) |
|
|
145 | (2) |
|
|
147 | (2) |
|
|
149 | (6) |
|
Other engineering and construction contracts |
|
|
149 | (1) |
|
|
150 | (1) |
|
Design Build and Operate Contract |
|
|
150 | (1) |
|
Professional service contracts |
|
|
150 | (1) |
|
|
151 | (1) |
|
|
152 | (1) |
|
Facilities management contracts |
|
|
153 | (1) |
|
|
154 | (1) |
|
17 The effect of Z clauses |
|
|
155 | (16) |
|
The good, the bad, and the downright ugly |
|
|
155 | (2) |
|
|
157 | (14) |
|
18 Disputes concerning Defined Cost and compensation events |
|
|
171 | (4) |
|
|
171 | (1) |
|
|
172 | (2) |
|
How are disputes dealt with formally? |
|
|
174 | (1) |
|
19 Defined Cost in termination |
|
|
175 | (2) |
Index |
|
177 | |