The author |
|
v | |
Preface |
|
vii | |
Acknowledgements |
|
ix | |
Table of cases |
|
xix | |
Table of legislation |
|
xxxiii | |
Chapter 1 Introduction To Construction Disputes |
|
1 | (40) |
|
Applicable principles of law |
|
|
1 | (1) |
|
|
1 | (5) |
|
|
2 | (1) |
|
|
2 | (3) |
|
|
5 | (1) |
|
|
6 | (3) |
|
|
7 | (2) |
|
Differences between common and civil law |
|
|
9 | (1) |
|
|
9 | (9) |
|
|
10 | (4) |
|
Enforcement of adjudication decisions versus arbitration awards |
|
|
14 | (4) |
|
The historical development of dispute resolution in construction matters |
|
|
18 | (1) |
|
The legal development of other dispute resolution methods |
|
|
19 | (5) |
|
The engineer/arbitrator as judge |
|
|
20 | (2) |
|
The engineer as quasi-arbitrator |
|
|
22 | (2) |
|
The development of non-statutory adjudication |
|
|
24 | (10) |
|
The advent of Dispute Boards in England |
|
|
27 | (1) |
|
Extension to international cases |
|
|
28 | (3) |
|
Specific regional differences and methods |
|
|
31 | (3) |
|
Forms of standard construction contracts |
|
|
34 | (4) |
|
|
35 | (1) |
|
|
36 | (1) |
|
Methods of construction contracting |
|
|
36 | (2) |
|
Contractual operational and payment formats |
|
|
38 | (3) |
|
The traditional lump sum or fixed price contract |
|
|
38 | (1) |
|
The guaranteed maximum price contract |
|
|
39 | (1) |
|
The remeasurement type of contract |
|
|
39 | (1) |
|
The cost reimbursement or cost plus fee contract |
|
|
40 | (1) |
|
|
40 | (1) |
Chapter 2 The Construction Contract |
|
41 | (32) |
|
|
41 | (9) |
|
|
41 | (1) |
|
|
42 | (2) |
|
|
44 | (1) |
|
|
44 | (1) |
|
|
45 | (2) |
|
Intent to be legally bound |
|
|
47 | (1) |
|
|
47 | (1) |
|
|
48 | (1) |
|
|
49 | (1) |
|
Other contract issues battle of the forms and related difficulties |
|
|
50 | (2) |
|
|
52 | (4) |
|
Unilateral versus bilateral contracts |
|
|
56 | (1) |
|
|
56 | (1) |
|
Conditions as terms of a contract |
|
|
56 | (2) |
|
|
57 | (1) |
|
|
57 | (1) |
|
|
58 | (15) |
|
|
60 | (1) |
|
Express false representations |
|
|
60 | (2) |
|
Implied misrepresentations |
|
|
62 | (1) |
|
Negligent misrepresentations |
|
|
62 | (1) |
|
Innocent misrepresentations |
|
|
62 | (1) |
|
Misstatements of the law versus fact |
|
|
62 | (1) |
|
|
63 | (1) |
|
|
63 | (3) |
|
|
66 | (1) |
|
|
67 | (2) |
|
Mistake versus frustration versus impossibility |
|
|
69 | (4) |
Chapter 3 Design Disputes And Liability |
|
73 | (36) |
|
|
73 | (36) |
|
The design professional: architect/engineer's duty tort versus contract |
|
|
75 | (1) |
|
Fitness for purpose liability |
|
|
76 | (2) |
|
Reasonable skill and care |
|
|
78 | (1) |
|
Concurrent negligence and contract duty |
|
|
79 | (13) |
|
Duty to warn of retrospective danger |
|
|
92 | (5) |
|
|
97 | (1) |
|
|
97 | (2) |
|
Miscellaneous matters: personal injury, latent defects and subsequent occupiers |
|
|
99 | (2) |
|
|
101 | (2) |
|
|
103 | (1) |
|
Matters other than design |
|
|
104 | (1) |
|
New, novel and strict design standards |
|
|
105 | (1) |
|
Liability for design of others |
|
|
106 | (3) |
Chapter 4 Site Conditions |
|
109 | (16) |
|
|
109 | (6) |
|
|
109 | (1) |
|
|
110 | (1) |
|
Does the contractor have a licence to enter the site? |
|
|
111 | (4) |
|
|
115 | (10) |
|
Site access after completion |
|
|
116 | (1) |
|
|
116 | (1) |
|
Unforeseen ground conditions |
|
|
117 | (2) |
|
Contract provisions for unexpected ground conditions |
|
|
119 | (2) |
|
Misrepresentation of the site conditions |
|
|
121 | (1) |
|
The site under the Housing Grants Act |
|
|
122 | (2) |
|
Employer responsibility regarding possession |
|
|
124 | (1) |
Chapter 5 The Subcontractor |
|
125 | (14) |
|
|
125 | (2) |
|
Relations with the contractor |
|
|
126 | (1) |
|
Employer insolvency and payments |
|
|
126 | (1) |
|
|
127 | (8) |
|
|
127 | (2) |
|
|
129 | (2) |
|
Problems with nominated subcontractors |
|
|
131 | (4) |
|
|
135 | (1) |
|
|
135 | (1) |
|
The Contracts (Rights of Third Parties) Act 1999 |
|
|
135 | (4) |
|
|
135 | (1) |
|
Relations with architect and engineer |
|
|
136 | (3) |
Chapter 6 Defences To Construction Disputes |
|
139 | (14) |
|
|
139 | (5) |
|
Is the contract terminated? |
|
|
141 | (1) |
|
|
142 | (1) |
|
The purpose of force majeure clauses historically and internationally |
|
|
143 | (1) |
|
Typical force majeure clause usage |
|
|
144 | (4) |
|
The necessary requirements for force majeure |
|
|
145 | (1) |
|
When does force majeure commence |
|
|
146 | (1) |
|
The duration of the condition |
|
|
146 | (1) |
|
When should notice be given |
|
|
147 | (1) |
|
|
147 | (1) |
|
|
148 | (5) |
Chapter 7 Issues Regarding Contractors' Rights And Obligations Under Standard Form Agreements |
|
153 | (26) |
|
Design-build form contracts |
|
|
154 | (10) |
|
Particular provisions such as Extension of Time clauses |
|
|
156 | (1) |
|
EOT "sweeping-up" clauses |
|
|
157 | (1) |
|
The other major forms of contract |
|
|
157 | (1) |
|
The JCT forms of contract |
|
|
157 | (2) |
|
JCT 98 Standard Form of Building Contract (JCT 98 SFBC) |
|
|
159 | (1) |
|
The changes made in the SBC05 |
|
|
159 | (2) |
|
|
161 | (1) |
|
|
162 | (1) |
|
Commencement, progress and completion |
|
|
162 | (1) |
|
Warranties/third party rights |
|
|
163 | (1) |
|
|
163 | (1) |
|
|
164 | (1) |
|
The ICE conditions of contract |
|
|
164 | (6) |
|
Measurement Version 7th Edition |
|
|
164 | (1) |
|
ICE Design and Construct contract |
|
|
164 | (1) |
|
|
165 | (1) |
|
Time and cost issues under the Measurement Version, Design and Construct, Minor Works |
|
|
165 | (1) |
|
The NEC3 the New Engineering Contract Engineering and Construction Contract NEC ECC |
|
|
166 | (1) |
|
|
167 | (1) |
|
Some important provisions |
|
|
167 | (2) |
|
|
169 | (1) |
|
|
169 | (1) |
|
|
170 | (1) |
|
Payment for defective work |
|
|
170 | (1) |
|
The FIDIC Forms of Contract |
|
|
170 | (1) |
|
The three main FIDIC Forms of Contract |
|
|
170 | (1) |
|
|
171 | (1) |
|
Employer design of the project |
|
|
171 | (1) |
|
Contractor design of the project |
|
|
171 | (1) |
|
Common issues between the forms |
|
|
172 | (4) |
|
|
172 | (1) |
|
|
172 | (1) |
|
|
173 | (1) |
|
Contractor's rights and obligations |
|
|
173 | (2) |
|
Additional obligations and issues |
|
|
175 | (1) |
|
|
175 | (1) |
|
|
175 | (1) |
|
|
176 | (3) |
|
|
176 | (1) |
|
|
176 | (1) |
|
|
177 | (2) |
Chapter 8 Termination Of Contract |
|
179 | (16) |
|
Termination versus determination |
|
|
179 | (16) |
|
Common law repudiation versus determination |
|
|
184 | (1) |
|
Can suspension be repudiation? |
|
|
185 | (1) |
|
|
186 | (1) |
|
A repudiation need not be accepted |
|
|
187 | (1) |
|
|
188 | (1) |
|
|
189 | (2) |
|
|
191 | (1) |
|
Waiver and promissory estoppel |
|
|
192 | (3) |
Chapter 9 The Certification Process |
|
195 | (34) |
|
|
195 | (5) |
|
|
197 | (1) |
|
|
197 | (1) |
|
|
198 | (1) |
|
Impartiality of the certifier |
|
|
199 | (1) |
|
|
200 | (10) |
|
|
200 | (10) |
|
|
210 | (15) |
|
Is it a variation or a separate contract? |
|
|
210 | (5) |
|
|
215 | (1) |
|
|
215 | (1) |
|
Failure to order a variation |
|
|
216 | (1) |
|
|
217 | (2) |
|
What is the basis for payment and value of the variation? |
|
|
219 | (2) |
|
|
221 | (2) |
|
Standard methods of measurement |
|
|
223 | (1) |
|
|
224 | (1) |
|
|
224 | (1) |
|
|
225 | (4) |
Chapter 10 Types Of Claims |
|
229 | (46) |
|
|
229 | (46) |
|
|
230 | (5) |
|
|
235 | (3) |
|
Money damages but at what cost |
|
|
238 | (3) |
|
|
241 | (3) |
|
Contract versus tort damages |
|
|
244 | (4) |
|
|
248 | (1) |
|
Liquidated damages and claims for extensions of time |
|
|
249 | (7) |
|
|
256 | (1) |
|
|
257 | (1) |
|
|
258 | (1) |
|
Who determines the extension |
|
|
259 | (2) |
|
|
261 | (1) |
|
|
262 | (3) |
|
|
265 | (8) |
|
|
273 | (2) |
Chapter 11 Collateral Warranties |
|
275 | (8) |
|
Collateral warranty provisions |
|
|
276 | (7) |
|
The Contracts (Rights of Third Parties) Act 1999 |
|
|
277 | (1) |
|
Enforcing variation and rescission of contract |
|
|
278 | (1) |
|
|
279 | (1) |
|
The promisee's enforcement of the contract |
|
|
280 | (1) |
|
|
281 | (2) |
Chapter 12 Non-Contract Liability |
|
283 | (32) |
|
|
283 | (32) |
|
|
298 | (1) |
|
The "Assumption of Responsibility Test" |
|
|
299 | (1) |
|
|
300 | (1) |
|
|
300 | (1) |
|
|
301 | (6) |
|
|
307 | (2) |
|
|
309 | (1) |
|
Strict liability in nuisance the rule in Rylands v Fletcher |
|
|
310 | (3) |
|
|
313 | (1) |
|
|
314 | (1) |
Chapter 13 Time At Large And Time-Bar Clauses |
|
315 | (18) |
|
|
315 | (10) |
|
|
325 | (8) |
Chapter 14 Dispute Resolution |
|
333 | (44) |
|
|
333 | (4) |
|
Litigation versus arbitration versus mediation |
|
|
336 | (1) |
|
|
337 | (2) |
|
|
337 | (1) |
|
|
337 | (2) |
|
|
339 | (2) |
|
|
339 | (1) |
|
|
340 | (1) |
|
Mediation during the litigation/arbitration process |
|
|
340 | (1) |
|
|
341 | (8) |
|
Enforceability of ADR agreements and mediation settlement agreements |
|
|
345 | (1) |
|
Withdrawing from mediation |
|
|
346 | (1) |
|
Refusing to mediate no cost consequences |
|
|
346 | (2) |
|
|
348 | (1) |
|
|
349 | (6) |
|
The process under the Act |
|
|
349 | (1) |
|
The Scheme for construction contracts |
|
|
350 | (1) |
|
The Act's main areas is there a dispute? |
|
|
351 | (2) |
|
Does the dispute arise under a construction contract? |
|
|
353 | (1) |
|
Does a contract have to be in writing within the meaning of section 107? |
|
|
354 | (1) |
|
|
355 | (7) |
|
Procedures under the Scheme |
|
|
358 | (1) |
|
|
358 | (1) |
|
Appointment of an adjudicator |
|
|
358 | (1) |
|
|
359 | (1) |
|
Adjudicator's powers and duties |
|
|
359 | (1) |
|
Changes to the Housing Grants Act |
|
|
360 | (2) |
|
|
362 | (5) |
|
|
362 | (2) |
|
What makes a Dispute Board unique? What can be achieved by using a Dispute Board? |
|
|
364 | (1) |
|
Non-binding recommendations |
|
|
364 | (2) |
|
Interim-binding decisions |
|
|
366 | (1) |
|
History of Dispute Boards |
|
|
366 | (1) |
|
|
367 | (1) |
|
Harmonised contract conditions |
|
|
368 | (9) |
|
|
368 | (1) |
|
An overview composition of Dispute Boards and their operation |
|
|
369 | (1) |
|
Appointment and membership |
|
|
370 | (1) |
|
The importance of early appointment and of regular site visits |
|
|
371 | (1) |
|
|
371 | (1) |
|
|
372 | (1) |
|
|
373 | (1) |
|
Dispute Review Board costs |
|
|
374 | (1) |
|
|
374 | (2) |
|
|
376 | (1) |
Chapter 15 Key Issues In Dispute Resolution |
|
377 | (50) |
|
|
377 | (11) |
|
|
386 | (2) |
|
|
388 | (10) |
|
The Chartered Institute of Arbitrators Protocol for E-disclosure in Arbitration |
|
|
390 | (2) |
|
|
392 | (1) |
|
Enforcement of foreign awards in the UK |
|
|
393 | (5) |
|
Serial adjudication decisions |
|
|
398 | (10) |
|
|
398 | (1) |
|
|
398 | (8) |
|
|
406 | (2) |
|
Arbitration of Dispute Board decisions |
|
|
408 | (1) |
|
Notice of dissatisfaction |
|
|
408 | (1) |
|
|
409 | (1) |
|
|
409 | (18) |
|
|
409 | (3) |
|
|
412 | (2) |
|
|
414 | (4) |
|
|
418 | (3) |
|
|
421 | (6) |
Appendices |
|
427 | (216) |
|
Appendix 1 Glossary of construction terms |
|
|
427 | (18) |
|
Appendix 2 Housing Grants, Construction and Regeneration Act 1996 |
|
|
445 | (10) |
|
Appendix 3 The Scheme for Construction Contracts (England and Wales) Regulations 1998 |
|
|
455 | (12) |
|
Appendix 4 Contracts (Rights of Third Parties) Act 1999 |
|
|
467 | (8) |
|
Appendix 5 Dispute Board provisions under the FIDIC Red Book |
|
|
475 | (14) |
|
Appendix 6 Dispute Board provisions under the FIDIC Yellow Book |
|
|
489 | (12) |
|
Appendix 7 Dispute Board provisions under the FIDIC Silver Book |
|
|
501 | (12) |
|
Appendix 8 ICC Dispute Board Rules |
|
|
513 | (20) |
|
Appendix 9 The Dispute Board Federation Dispute Adjudication Board Ad Hoc DAB Rules |
|
|
533 | (12) |
|
Appendix 10 The Defective Premises Act 1972 |
|
|
545 | (6) |
|
Appendix 11 Unfair Contract Terms Act 1977 |
|
|
551 | (8) |
|
Appendix 12 Torts (Interference with Goods) Act 1977 |
|
|
559 | (8) |
|
Appendix 13 Sale of Goods Act 1979 |
|
|
567 | (20) |
|
Appendix 14 Limitation Act 1980 |
|
|
587 | (30) |
|
Appendix 15 Supply of Goods and Services Act 1982 |
|
|
617 | (20) |
|
Appendix 16 Latent Damage Act 1986 |
|
|
637 | (6) |
Index |
|
643 | |