Preface |
|
xiii | |
Acknowledgments |
|
xv | |
Author |
|
xvii | |
Abbreviations |
|
xix | |
|
|
1 | (4) |
|
|
1 | (1) |
|
|
2 | (1) |
|
|
2 | (1) |
|
|
2 | (1) |
|
|
3 | (2) |
|
Chapter 2 Construction Contract |
|
|
5 | (22) |
|
|
5 | (1) |
|
2.2 Standard Forms of Contract |
|
|
5 | (1) |
|
|
6 | (6) |
|
|
6 | (1) |
|
2.3.2 FIDIC Contract Components |
|
|
7 | (1) |
|
2.3.2.1 General Conditions |
|
|
7 | (2) |
|
2.3.2.2 Particular Conditions |
|
|
9 | (2) |
|
2.3.2.3 Supplement Documents |
|
|
11 | (1) |
|
|
12 | (6) |
|
|
13 | (1) |
|
|
13 | (3) |
|
|
16 | (1) |
|
|
17 | (1) |
|
|
18 | (2) |
|
|
18 | (1) |
|
2.5.2 JCT Contract Components |
|
|
19 | (1) |
|
|
20 | (2) |
|
|
20 | (1) |
|
2.6.2 Contract Interpretation |
|
|
20 | (1) |
|
|
21 | (1) |
|
|
21 | (1) |
|
|
21 | (1) |
|
|
21 | (1) |
|
|
22 | (3) |
|
|
22 | (1) |
|
2.7.2 Formation of a Contract |
|
|
23 | (1) |
|
|
23 | (1) |
|
2.7.4 Types of Contract: Public or Private |
|
|
23 | (1) |
|
2.7.5 Standard Forms of Contract |
|
|
24 | (1) |
|
2.7.6 Limitation of Liability |
|
|
24 | (1) |
|
2.7.7 Liquidated Damages and Penalty |
|
|
24 | (1) |
|
|
25 | (1) |
|
|
25 | (1) |
|
|
26 | (1) |
|
Chapter 3 Time Management |
|
|
27 | (46) |
|
|
27 | (1) |
|
3.2 Legal Obligation of Completion |
|
|
27 | (6) |
|
3.2.1 Terminology of Completion |
|
|
27 | (1) |
|
3.2.1.1 Substantial Completion |
|
|
27 | (1) |
|
3.2.1.2 Practical Completion |
|
|
28 | (1) |
|
|
29 | (1) |
|
3.2.1.4 Planned Completion |
|
|
29 | (1) |
|
3.2.1.5 Completion Date or Time/Date for Completion |
|
|
29 | (1) |
|
3.2.2 Contract Express Provisions |
|
|
29 | (1) |
|
|
29 | (1) |
|
|
30 | (1) |
|
|
30 | (1) |
|
|
30 | (1) |
|
|
31 | (1) |
|
|
31 | (1) |
|
3.2.3.2 Consumer Rights Act 2015 |
|
|
31 | (1) |
|
|
31 | (1) |
|
3.2.4 Time Is of the Essence |
|
|
32 | (1) |
|
|
33 | (13) |
|
|
33 | (1) |
|
3.3.1.1 Baseline Programme |
|
|
33 | (1) |
|
3.3.1.2 Stakeholder Engagement |
|
|
33 | (1) |
|
3.3.1.3 Work Breakdown Structure (WBS) |
|
|
33 | (1) |
|
|
33 | (1) |
|
|
34 | (1) |
|
3.3.2 Programme under NEC Contract |
|
|
34 | (2) |
|
|
36 | (1) |
|
3.3.2.2 Accepted Programme |
|
|
36 | (1) |
|
3.3.2.3 Revising the Programme |
|
|
37 | (1) |
|
3.3.2.4 Activity Schedule |
|
|
38 | (1) |
|
3.3.2.5 Sectional Completion |
|
|
38 | (2) |
|
3.3.2.6 Bonus for Early Completion |
|
|
40 | (1) |
|
|
40 | (1) |
|
3.3.3 Programme under FIDIC Contract |
|
|
40 | (1) |
|
3.3.3.1 General Programme Requirement |
|
|
41 | (1) |
|
3.3.3.2 Revised Programme |
|
|
41 | (1) |
|
3.3.3.3 Process and Time Limit for Programme Submission and Acceptance |
|
|
42 | (1) |
|
|
43 | (1) |
|
3.3.4 Time Management under JCT Contract |
|
|
43 | (1) |
|
|
43 | (1) |
|
|
44 | (1) |
|
|
44 | (1) |
|
|
45 | (1) |
|
|
45 | (1) |
|
3.3.4.6 Liquidated Damages |
|
|
46 | (1) |
|
|
46 | (10) |
|
|
46 | (2) |
|
3.4.2 Extension of Time (EOT) |
|
|
48 | (1) |
|
|
49 | (2) |
|
3.4.3.1 As-Planned vs. As-Built |
|
|
51 | (2) |
|
3.4.3.2 Impacted As-Planned |
|
|
53 | (1) |
|
3.4.3.3 Time Impact Analysis |
|
|
53 | (1) |
|
3.4.3.4 Collapsed As-Built |
|
|
54 | (1) |
|
|
55 | (1) |
|
|
56 | (12) |
|
3.5.1 Prevention Principle |
|
|
56 | (1) |
|
|
57 | (1) |
|
|
58 | (1) |
|
3.5.3.1 English Law -- Malmaison Approach |
|
|
59 | (1) |
|
3.5.3.2 Scottish Law -- Appointment Approach |
|
|
59 | (1) |
|
3.5.3.3 US Law -- Multiple Approaches |
|
|
60 | (1) |
|
|
60 | (2) |
|
|
62 | (1) |
|
|
62 | (2) |
|
|
64 | (1) |
|
3.5.4.3 Standard Forms Contract |
|
|
64 | (1) |
|
|
64 | (1) |
|
|
65 | (1) |
|
|
65 | (1) |
|
|
66 | (1) |
|
3.5.5.1 Who Owns the Float? |
|
|
66 | (2) |
|
3.5.6 Time Bar and Condition Precedent |
|
|
68 | (1) |
|
|
68 | (2) |
|
|
70 | (3) |
|
Chapter 4 Cost Management |
|
|
73 | (30) |
|
|
73 | (1) |
|
|
73 | (3) |
|
|
73 | (1) |
|
|
73 | (1) |
|
|
74 | (1) |
|
|
74 | (1) |
|
4.2.2 Statutory Obligation |
|
|
74 | (1) |
|
4.2.3 Employer's Obligation |
|
|
75 | (1) |
|
4.2.4 Contractor's Obligation |
|
|
76 | (1) |
|
4.3 Cost Management under FIDIC Contract |
|
|
76 | (3) |
|
4.3.1 Adjust the Contract Price |
|
|
76 | (1) |
|
|
77 | (1) |
|
|
77 | (1) |
|
|
78 | (1) |
|
|
79 | (1) |
|
4.4 Cost Management under NEC Contract |
|
|
79 | (9) |
|
|
79 | (1) |
|
4.4.1.1 Payment Components |
|
|
80 | (1) |
|
|
80 | (1) |
|
4.4.1.3 Payment Assessment |
|
|
81 | (1) |
|
|
82 | (1) |
|
|
83 | (1) |
|
|
84 | (1) |
|
|
85 | (1) |
|
|
86 | (1) |
|
|
86 | (1) |
|
4.4.6.1 Target Cost Pain/Gain Share under Options C and D |
|
|
87 | (1) |
|
4.4.6.2 Option X20 -- Key Performance Indicators (KPIs) |
|
|
87 | (1) |
|
4.4.7 Price Adjustment for Inflation |
|
|
87 | (1) |
|
4.5 Cost Management under JCT Contract |
|
|
88 | (5) |
|
|
89 | (1) |
|
|
89 | (1) |
|
|
90 | (1) |
|
|
91 | (1) |
|
4.5.3 Claim for Loss and Expense |
|
|
92 | (1) |
|
|
92 | (1) |
|
|
93 | (6) |
|
|
93 | (1) |
|
4.6.2 Home Office Overhead (HOO) |
|
|
94 | (1) |
|
|
94 | (1) |
|
|
94 | (1) |
|
|
95 | (1) |
|
|
96 | (1) |
|
|
97 | (2) |
|
|
99 | (1) |
|
|
100 | (3) |
|
Chapter 5 Risk Management |
|
|
103 | (36) |
|
|
103 | (1) |
|
5.2 Standard Risk Management Procedure |
|
|
103 | (5) |
|
5.2.1 Risk Identification |
|
|
104 | (1) |
|
|
105 | (1) |
|
5.2.2.1 Qualitative Analysis |
|
|
105 | (2) |
|
5.2.2.2 Quantitative Analysis |
|
|
107 | (1) |
|
|
108 | (1) |
|
5.2.4 Risk Monitoring and Control |
|
|
108 | (1) |
|
5.3 Risk Management under NEC Forms of Contract |
|
|
108 | (6) |
|
|
109 | (1) |
|
|
109 | (1) |
|
|
109 | (1) |
|
|
110 | (1) |
|
5.3.1.4 Compensation Event |
|
|
110 | (1) |
|
5.3.1.5 Secondary Options |
|
|
110 | (2) |
|
|
112 | (1) |
|
|
113 | (1) |
|
5.4 Risk Management under FIDIC Forms of Contract |
|
|
114 | (5) |
|
|
114 | (1) |
|
|
114 | (2) |
|
5.4.1.2 Contractor's Risk |
|
|
116 | (1) |
|
5.4.1.3 Exceptional Events |
|
|
117 | (1) |
|
|
118 | (1) |
|
|
119 | (9) |
|
|
119 | (1) |
|
5.5.2 QSRA (Quantitative Schedule Risk Analysis) |
|
|
119 | (1) |
|
5.5.2.1 Duration Uncertainty |
|
|
120 | (3) |
|
|
123 | (4) |
|
5.5.2.3 Programme Confidence |
|
|
127 | (1) |
|
5.5.3 Critical Path and What-if Scenarios |
|
|
128 | (1) |
|
|
128 | (7) |
|
5.6.1 Types of Cost Reserve |
|
|
130 | (1) |
|
5.6.1.1 Contingency Reserve |
|
|
131 | (1) |
|
5.6.1.2 Management Reserve |
|
|
131 | (1) |
|
5.6.2 QCRA (Quantitative Cost Risk Analysis) |
|
|
131 | (2) |
|
5.6.3 QSCRA (Quantitative Schedule and Cost Risk Analysis) |
|
|
133 | (1) |
|
|
133 | (2) |
|
|
135 | (1) |
|
|
136 | (3) |
|
Chapter 6 Change Management |
|
|
139 | (28) |
|
|
139 | (1) |
|
|
139 | (1) |
|
|
140 | (3) |
|
6.3.1 Claim Inside the Contract |
|
|
140 | (1) |
|
|
140 | (1) |
|
|
141 | (2) |
|
6.3.2 Claim Outside the Contract |
|
|
143 | (1) |
|
|
143 | (4) |
|
|
144 | (2) |
|
|
146 | (1) |
|
|
146 | (1) |
|
|
146 | (1) |
|
6.5 Compensation Event under NEC |
|
|
147 | (12) |
|
|
149 | (1) |
|
6.5.1.1 Events Resulting from the Client or Their Representative |
|
|
150 | (1) |
|
6.5.1.2 Events Outside the Client's Control |
|
|
151 | (1) |
|
|
152 | (5) |
|
|
157 | (1) |
|
|
158 | (1) |
|
|
159 | (2) |
|
|
160 | (1) |
|
|
160 | (1) |
|
6.7 Change Management under PMBOK |
|
|
161 | (1) |
|
|
161 | (1) |
|
6.8 Change Theme under PRINCE2 |
|
|
161 | (1) |
|
|
162 | (2) |
|
6.9.1 Conditions Precedent |
|
|
162 | (1) |
|
|
163 | (1) |
|
|
164 | (1) |
|
|
165 | (2) |
|
Chapter 7 Alternative Dispute Resolutions |
|
|
167 | (30) |
|
|
167 | (1) |
|
7.2 Alternative Dispute Resolution |
|
|
167 | (1) |
|
|
168 | (1) |
|
|
169 | (3) |
|
7.4.1 Statutory Adjudication |
|
|
169 | (2) |
|
7.4.2 Non-Statutory Adjudication |
|
|
171 | (1) |
|
|
172 | (3) |
|
7.5.1 Dispute Avoidance Board |
|
|
174 | (1) |
|
7.5.2 Dispute Review Board/Dispute Resolution Board (DRB) |
|
|
174 | (1) |
|
7.5.3 Dispute Adjudication Board |
|
|
174 | (1) |
|
|
175 | (4) |
|
7.6.1 Arbitration vs. Litigation |
|
|
175 | (1) |
|
|
176 | (3) |
|
7.7 Dispute Resolution in Standard Forms |
|
|
179 | (12) |
|
|
180 | (1) |
|
7.7.1.1 Tier 1 -- Engineer's Determination |
|
|
180 | (1) |
|
7.7.1.2 Tier 2 -- Dispute Avoidance and Adjudication Board |
|
|
181 | (1) |
|
7.7.1.3 Tier 3 -- Arbitration |
|
|
182 | (1) |
|
|
183 | (1) |
|
7.7.2.1 Tier 1 -- Negotiation |
|
|
183 | (2) |
|
7.7.2.2 Tier 2 -- Adjudication/Dispute Avoidance Board |
|
|
185 | (3) |
|
7.7.2.3 Tier 3 -- Tribunal |
|
|
188 | (1) |
|
|
188 | (1) |
|
7.7.3.1 Tier 1 -- Negotiation |
|
|
189 | (1) |
|
7.7.3.2 Tier 2 -- Mediation/Adjudication |
|
|
189 | (1) |
|
7.7.3.3 Tier 3 -- Arbitration/Litigation |
|
|
190 | (1) |
|
|
191 | (3) |
|
|
192 | (1) |
|
|
193 | (1) |
|
|
194 | (3) |
|
Chapter 8 Integrated Project Control |
|
|
197 | (22) |
|
|
197 | (1) |
|
8.2 Integrated Project Control System |
|
|
197 | (5) |
|
8.2.1 Integrated Project Control |
|
|
197 | (1) |
|
|
197 | (2) |
|
8.2.1.2 Post-Contract: Front-End Tool and System |
|
|
199 | (1) |
|
8.2.1.3 Post-Contract: During Implementation |
|
|
200 | (1) |
|
8.2.2 Programme and Portfolio Management |
|
|
201 | (1) |
|
8.3 Project Control Procedure |
|
|
202 | (13) |
|
8.3.1 Earned Value Management |
|
|
202 | (5) |
|
|
207 | (2) |
|
|
209 | (1) |
|
|
210 | (1) |
|
|
211 | (1) |
|
8.3.6 Performance Reporting |
|
|
211 | (4) |
|
8.4 Continuous Performance Improvement |
|
|
215 | (1) |
|
8.4.1 Key Performance Indicators (KPI) |
|
|
215 | (1) |
|
|
215 | (1) |
|
|
216 | (1) |
|
|
217 | (2) |
Index |
|
219 | |