Introduction |
|
xiii | |
|
|
xiii | |
|
The Step by Step approach |
|
|
xiii | |
|
Download the practice files |
|
|
xiv | |
|
|
xv | |
|
Sidebar: Adapt procedure steps |
|
|
xvi | |
|
Get support and give feedback |
|
|
xviii | |
|
|
xviii | |
|
|
xviii | |
|
|
xviii | |
Part 1: Get started with Microsoft Project |
|
|
1 Project, project management, and you |
|
|
3 | (8) |
|
|
4 | (2) |
|
Meet the Project family See the new features in Project 2016 |
|
|
6 | (1) |
|
What was new in Project 2013 |
|
|
6 | (1) |
|
What was new in Project 2010 |
|
|
7 | (2) |
|
Take a project manager's perspective |
|
|
9 | (1) |
|
|
10 | (1) |
|
|
11 | (26) |
|
Explore the Project user interface |
|
|
12 | (7) |
|
Manage files and set options in the Backstage view |
|
|
19 | (4) |
|
Sidebar: Templates: Avoid reinventing the wheel |
|
|
21 | (2) |
|
Work with schedule details in views |
|
|
23 | (5) |
|
Use reports to check a plan's status |
|
|
28 | (3) |
|
|
31 | (1) |
|
|
32 | (5) |
Part 2: Simple scheduling basics |
|
|
|
37 | (10) |
|
Create a new plan and set its start date |
|
|
38 | (1) |
|
Set nonworking days in the project calendar |
|
|
39 | (4) |
|
Enter the plan title and other properties |
|
|
43 | (1) |
|
Sidebar: Project management focus: Project is part of a larger picture |
|
|
44 | (1) |
|
|
44 | (1) |
|
|
45 | (2) |
|
|
47 | (32) |
|
|
48 | (2) |
|
Sidebar: Project management focus: Defining the right tasks for the deliverable |
|
|
49 | (1) |
|
Enter task durations and dates |
|
|
50 | (5) |
|
Sidebar: Project management focus: How do you come up with accurate task durations? |
|
|
52 | (3) |
|
|
55 | (1) |
|
Create summary tasks to outline the plan |
|
|
56 | (3) |
|
Sidebar: Project management focus: Top-down and bottom-up planning |
|
|
57 | (2) |
|
Link tasks to create dependencies |
|
|
59 | (4) |
|
Switch task scheduling from manual to automatic |
|
|
63 | (2) |
|
Check a plan's duration and finish date |
|
|
65 | (2) |
|
Document task information |
|
|
67 | (2) |
|
|
69 | (1) |
|
|
70 | (9) |
|
|
79 | (22) |
|
|
80 | (2) |
|
Sidebar: Equipment resource considerations |
|
|
82 | (1) |
|
Enter the maximum capacity for work resources |
|
|
82 | (2) |
|
Enter work resource pay rates |
|
|
84 | (3) |
|
Sidebar: Project management focus: Getting resource cost information |
|
|
86 | (1) |
|
Adjust working time in a resource calendar |
|
|
87 | (4) |
|
|
91 | (1) |
|
Document resources by using notes |
|
|
92 | (2) |
|
|
94 | (1) |
|
|
95 | (6) |
|
6 Assign resources to tasks |
|
|
101 | (26) |
|
Assign work resources to tasks |
|
|
102 | (5) |
|
Control work when adding or removing resource assignments |
|
|
107 | (7) |
|
Sidebar: Project management focus: When should effort-driven scheduling apply? |
|
|
112 | (2) |
|
Assign cost resources to tasks |
|
|
114 | (1) |
|
Check the plan after assigning resources |
|
|
115 | (4) |
|
|
119 | (1) |
|
|
120 | (7) |
|
7 Format and share your plan |
|
|
127 | (30) |
|
Customize a Gantt chart view |
|
|
128 | (6) |
|
Sidebar: Drawing on a Gantt chart |
|
|
131 | (3) |
|
Add tasks to a Timeline view |
|
|
134 | (5) |
|
Sidebar: Panning and zooming a Gantt chart view from a Timeline view |
|
|
138 | (1) |
|
|
139 | (2) |
|
|
141 | (3) |
|
|
144 | (3) |
|
|
147 | (1) |
|
|
148 | (9) |
|
8 Track progress: Basic techniques |
|
|
157 | (22) |
|
Understand progress tracking |
|
|
158 | (1) |
|
Save a baseline of your plan |
|
|
159 | (4) |
|
Track a plan as scheduled |
|
|
163 | (2) |
|
Enter a task's completion percentage |
|
|
165 | (3) |
|
Enter actual values for tasks |
|
|
168 | (3) |
|
Sidebar: Project management focus: Is the project on track? |
|
|
170 | (1) |
|
|
171 | (1) |
|
|
172 | (7) |
Part 3: Advanced scheduling techniques |
|
|
9 Fine-tune task scheduling |
|
|
179 | (34) |
|
See task relationships by using Task Path |
|
|
180 | (3) |
|
Adjust task link relationships |
|
|
183 | (3) |
|
Control task scheduling by using constraints |
|
|
186 | (8) |
|
|
194 | (2) |
|
Adjust working time for individual tasks |
|
|
196 | (3) |
|
Control task scheduling by using task types |
|
|
199 | (5) |
|
Sidebar: Assignment units, Peak, and the assignment calculation |
|
|
201 | (2) |
|
Sidebar: Task types and effort-driven scheduling |
|
|
203 | (1) |
|
See task schedule details by using the Task Inspector |
|
|
204 | (1) |
|
|
205 | (1) |
|
|
206 | (7) |
|
10 Fine-tune task details |
|
|
213 | (20) |
|
|
214 | (2) |
|
|
216 | (2) |
|
|
218 | (4) |
|
View the plan's critical path |
|
|
222 | (2) |
|
Schedule summary tasks manually |
|
|
224 | (2) |
|
|
226 | (1) |
|
|
227 | (6) |
|
11 Fine-tune resource and assignment details |
|
|
233 | (32) |
|
Change resource availability over multiple date ranges |
|
|
234 | (3) |
|
Work with multiple resource pay rates |
|
|
237 | (2) |
|
Change resource pay rates over different date ranges |
|
|
239 | (3) |
|
Delay the start of assignments |
|
|
242 | (1) |
|
Apply contours to assignments |
|
|
243 | (4) |
|
Create and assign material resources |
|
|
247 | (3) |
|
|
250 | (2) |
|
Adjust assignments in the Team Planner view (Project Professional only) |
|
|
252 | (3) |
|
|
255 | (1) |
|
|
256 | (9) |
|
12 Fine-tune the Project plan |
|
|
265 | (26) |
|
Examine resource allocations over time |
|
|
266 | (4) |
|
Sidebar: Project management focus: Evaluate resource allocation |
|
|
268 | (2) |
|
Resolve resource overallocations manually |
|
|
270 | (3) |
|
Level overallocated resources |
|
|
273 | (6) |
|
Check the plan's cost and finish date |
|
|
279 | (4) |
|
Sidebar: Project management focus: Finish date and critical tasks |
|
|
282 | (1) |
|
Inactivate tasks (Project Professional only) |
|
|
283 | (1) |
|
|
284 | (1) |
|
|
285 | (6) |
|
|
291 | (34) |
|
|
292 | (4) |
|
|
296 | (6) |
|
|
302 | (6) |
|
|
308 | (5) |
|
Sidebar: Create custom fields quickly |
|
|
310 | (3) |
|
|
313 | (4) |
|
|
317 | (1) |
|
|
318 | (7) |
|
14 Track progress: Detailed techniques |
|
|
325 | (24) |
|
|
326 | (4) |
|
Sidebar: Save interim plans |
|
|
328 | (2) |
|
Track actual and remaining work for tasks and assignments |
|
|
330 | (5) |
|
Sidebar: Enter actual costs manually |
|
|
334 | (1) |
|
Track timephased actual work for tasks and assignments |
|
|
335 | (7) |
|
Sidebar: Project management focus: Collect actuals from resources |
|
|
340 | (2) |
|
Reschedule incomplete work |
|
|
342 | (1) |
|
|
343 | (1) |
|
|
344 | (5) |
|
15 View and report project status |
|
|
349 | (24) |
|
Examine a plan's variance |
|
|
350 | (4) |
|
Sidebar: Project management focus: Get the word out |
|
|
353 | (1) |
|
Identify tasks that have slipped |
|
|
354 | (3) |
|
Sidebar: Project management focus: Is variance ever a good thing? |
|
|
356 | (1) |
|
|
357 | (5) |
|
|
362 | (4) |
|
|
366 | (1) |
|
|
367 | (6) |
Part 4: In-depth and special subjects |
|
|
16 Format and print views: In-depth techniques |
|
|
373 | (32) |
|
Format a Gantt chart view |
|
|
374 | (7) |
|
|
381 | (4) |
|
Format a Network Diagram view |
|
|
385 | (5) |
|
|
390 | (2) |
|
|
392 | (4) |
|
|
396 | (1) |
|
|
397 | (8) |
|
17 Format reports: In-depth techniques |
|
|
405 | (18) |
|
|
406 | (5) |
|
Sidebar: How reports compare to views |
|
|
409 | (2) |
|
Customize charts in a report |
|
|
411 | (4) |
|
Customize tables in a report |
|
|
415 | (2) |
|
|
417 | (1) |
|
|
418 | (5) |
|
|
423 | (22) |
|
Share custom elements between plans |
|
|
424 | (3) |
|
|
427 | (4) |
|
|
431 | (2) |
|
Customize the ribbon and Quick Access Toolbar |
|
|
433 | (5) |
|
|
438 | (1) |
|
|
439 | (6) |
|
19 Share information with other programs |
|
|
445 | (24) |
|
Copy Project data to and from other programs |
|
|
446 | (4) |
|
Open files in other formats in Project |
|
|
450 | (4) |
|
Save to other file formats from Project |
|
|
454 | (4) |
|
Sidebar: Share files with previous versions of Project |
|
|
457 | (1) |
|
Generate reports with Excel and Visio |
|
|
458 | (4) |
|
|
462 | (1) |
|
|
463 | (6) |
|
20 Consolidate projects and resources |
|
|
469 | (24) |
|
Share a resource pool across multiple plans |
|
|
470 | (10) |
|
Sidebar: Create a dedicated resource pool |
|
|
474 | (6) |
|
|
480 | (3) |
|
Sidebar: Keep consolidated plans simple |
|
|
482 | (1) |
|
Create dependencies between plans |
|
|
483 | (4) |
|
|
487 | (1) |
|
|
488 | (5) |
Appendix A: A short course in project management |
|
493 | (10) |
Appendix B: Develop your project-management skills |
|
503 | (4) |
Appendix C: Collaborate: Project, SharePoint, and PWA |
|
507 | (14) |
Appendix D: Use this book in a classroom |
|
521 | (6) |
Glossary |
|
527 | (10) |
Index |
|
537 | (20) |
About the authors |
|
557 | |